A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria

This paper examined labor productivity of floor tiling works in selected construction sites. Sixty one (61) sites were visited for the purpose of collecting data. The construction sites chosen for this study were ongoing one storey buildings in Abuja, Nigeria. Data used for the study were obtained...

Full description

Saved in:
Bibliographic Details
Main Authors: Idiake, J.E., Kabir, B., Shittu, A.A.
Format: Article
Language:English
Published: Penerbit UKM 2015
Online Access:http://journalarticle.ukm.my/9120/1/124-465-1-PB.pdf
http://journalarticle.ukm.my/9120/
http://spaj.ukm.my/jsb/index.php/jbp/issue/view/29
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Universiti Kebangsaan Malaysia
Language: English
id my-ukm.journal.9120
record_format eprints
spelling my-ukm.journal.91202016-12-14T06:49:02Z http://journalarticle.ukm.my/9120/ A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria Idiake, J.E. Kabir, B. Shittu, A.A. This paper examined labor productivity of floor tiling works in selected construction sites. Sixty one (61) sites were visited for the purpose of collecting data. The construction sites chosen for this study were ongoing one storey buildings in Abuja, Nigeria. Data used for the study were obtained using daily method of data collection which has the advantage to capture both quantity and time inputs. A total of 737 data points were collected for the floor tiling activity in all the sites. From these data, the study variables (cumulative productivity, baseline productivity, coefficient of variation and project performance index) were computed using conceptual (site-based) model of labor productivity measurement and the results revealed that many of the projects studied had low performance rating while few of projects performed well. A simple regression and correlation analyses were used to determine relationships of the research variables. The result showed that the coefficient of correlation between coefficient of labor productivity variability and performance index was found to be 0.588 which is significant at 0.01 confidence level. The coefficient of determination (R) was calculated to be 0.44. This showed that 44% variation in crew performance is accounted for by variability in labor productivity. It was suggested that crew performance in tiling work can be improved by moderating or curtailing variability in labor productivity. Penerbit UKM 2015 Article PeerReviewed application/pdf en http://journalarticle.ukm.my/9120/1/124-465-1-PB.pdf Idiake, J.E. and Kabir, B. and Shittu, A.A. (2015) A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria. Journal of Building Performance, 6 (1). pp. 32-39. ISSN 2180-2106 http://spaj.ukm.my/jsb/index.php/jbp/issue/view/29
institution Universiti Kebangsaan Malaysia
building Perpustakaan Tun Sri Lanang Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Kebangsaan Malaysia
content_source UKM Journal Article Repository
url_provider http://journalarticle.ukm.my/
language English
description This paper examined labor productivity of floor tiling works in selected construction sites. Sixty one (61) sites were visited for the purpose of collecting data. The construction sites chosen for this study were ongoing one storey buildings in Abuja, Nigeria. Data used for the study were obtained using daily method of data collection which has the advantage to capture both quantity and time inputs. A total of 737 data points were collected for the floor tiling activity in all the sites. From these data, the study variables (cumulative productivity, baseline productivity, coefficient of variation and project performance index) were computed using conceptual (site-based) model of labor productivity measurement and the results revealed that many of the projects studied had low performance rating while few of projects performed well. A simple regression and correlation analyses were used to determine relationships of the research variables. The result showed that the coefficient of correlation between coefficient of labor productivity variability and performance index was found to be 0.588 which is significant at 0.01 confidence level. The coefficient of determination (R) was calculated to be 0.44. This showed that 44% variation in crew performance is accounted for by variability in labor productivity. It was suggested that crew performance in tiling work can be improved by moderating or curtailing variability in labor productivity.
format Article
author Idiake, J.E.
Kabir, B.
Shittu, A.A.
spellingShingle Idiake, J.E.
Kabir, B.
Shittu, A.A.
A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria
author_facet Idiake, J.E.
Kabir, B.
Shittu, A.A.
author_sort Idiake, J.E.
title A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria
title_short A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria
title_full A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria
title_fullStr A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria
title_full_unstemmed A strategy for labor performance improvement for floor tiling work in single storey buildings in Abuja, Nigeria
title_sort strategy for labor performance improvement for floor tiling work in single storey buildings in abuja, nigeria
publisher Penerbit UKM
publishDate 2015
url http://journalarticle.ukm.my/9120/1/124-465-1-PB.pdf
http://journalarticle.ukm.my/9120/
http://spaj.ukm.my/jsb/index.php/jbp/issue/view/29
_version_ 1643737688262574080