Simulation and Analysis of Lightning Backflashover for the 132 Kv Kuala Krai–Gua Musang Transmission Line Using PSCAD
Lightning has been a major concern to the power system researchers as it may cause damage to the connected electrical equipment especially to the transmission line. One of the event that will cause lightning overvoltage and most likely to occur is backflashover. For that reason, one study has bee...
Saved in:
Main Author: | |
---|---|
Format: | Thesis |
Language: | English English |
Published: |
2009
|
Online Access: | http://psasir.upm.edu.my/id/eprint/7307/1/FK_2009_25a.pdf http://psasir.upm.edu.my/id/eprint/7307/ |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universiti Putra Malaysia |
Language: | English English |
Summary: | Lightning has been a major concern to the power system researchers as it may cause
damage to the connected electrical equipment especially to the transmission line. One of
the event that will cause lightning overvoltage and most likely to occur is backflashover.
For that reason, one study has been carried out where values of backflashover rate (BFR)
on a transmission line and probability of transformer damage at substation are observed
due to backflashover. A sample of worst performance of transmission line in Peninsular
Malaysia i.e. 132 kV Kuala Krai-Gua Musang transmission line data was obtained from
Tenaga Nasional Berhad (TNB) for the purpose of backflashover analysis. Power
System Computer Aided Design, PSCAD software was used to model integral part of
transmission line components such as insulator gap, tower and footing resistance
followed by doing the backflashover simulation and analysis. Besides that, the effects of
line parameters such as ground resistance, soil resistivity, tower surge impedance, tower height and number of shield wires in lightning performance study were also investigated.
Findings from backflashover analysis of Kuala Krai-Gua Musang transmission line
using PSCAD imply that the values of backflashover rate (BFR) and probability of
transformer damage are influenced by the values of line parameters. Right selection of
line parameters may reduce BFR and probability of transformer damage, thus improve
the transmission line performance. Findings of this research can be useful guideline
towards high voltage transmission line design and planning in Malaysia. |
---|