The discrete time/resource trade-off problem in project networks: A branch-and-bound approach
In many solution methods for resource-constrained project scheduling, it is assumed that both the duration of each activity and its resource requirements are known and fixed. In real-life projects, however, it often occurs that only one renewable bottleneck resource is available and that the activit...