National cement consumption is increasing along with the increasing of population and culture development. To fulfil the demand, cement factories need to increase they're production capacity. But to build a new factory will need a long time and a lot of money investment. So it is needed to find...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/10562 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | National cement consumption is increasing along with the increasing of population and culture development. To fulfil the demand, cement factories need to increase they're production capacity. But to build a new factory will need a long time and a lot of money investment. So it is needed to find different solution by modify existing factory without to much new investment to increase it's production capacity.<p> <br />
<br />
<br />
<br />
<br />
In Indonesia there are still old plants which have small production capacity (below 3000 TPD). The capacity can be increased by adding a calciner. Calciner is a burner to moved 90 % of calcination process (CaCO3→CaO+ CO2) from kiln.<p> <br />
<br />
<br />
<br />
<br />
But by increasing the capacity, the flow of gas and particle in the factory is also increased. Cyclone evaluation show that the old cyclones need to be modified or re-design. Conventional cyclone was designed by "Cylone design" software. Numerical simulation of the flow inside cyclone is done by application software FLUENT 6.0. Numerical simulation of the flow inside a conventional cyclone and yuril cyclone was done as comparation to designed cyclone.<p> <br />
<br />
<br />
<br />
<br />
The result of the simulation of the top cyclone show that the new cyclone based on design can work well in the new production capacity with efficiency of 88% and pressure drop of 67,45 mmH2O. |
---|