CRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR
Scheduling plays a very important role in a construction project. Each project has a duration that is determined from a variety of considerations. Schedule is a very useful tool to explain the activities required in the completion of a project. The ultimate goal is for the project to be completed on...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/24259 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:24259 |
---|---|
spelling |
id-itb.:242592017-09-27T10:25:49ZCRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR TERTIYANTONO (NIM : 15008042), SENO Indonesia Final Project INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/24259 Scheduling plays a very important role in a construction project. Each project has a duration that is determined from a variety of considerations. Schedule is a very useful tool to explain the activities required in the completion of a project. The ultimate goal is for the project to be completed on time and economically. <br /> <br /> <br /> ITB builds Labtek I and GKU II buildings in Jatinangor. Schedule plans both buildings began on June 23rd, 2012 and will be completed on December 23rd, 2012. However, due to various issues, the project has been delayed. Delay in the project could result in financial loss to the owner as well as the contractor, so the contractor should make up the delays by speeding up project activities on the critical path by adding more labors, tools, method change, material change, etc. This is called a crash program. <br /> <br /> <br /> One of crash program that is implemented by the contractor is on the wall construction. Alternative methods of crashing that can be done are replacing wall material, adding labors, and adding the work hours. <br /> <br /> <br /> From the analysis conducted found that doing a crash program by replacing the common red brick to lightweight brick on the GKU II’s first floor wall work, produces an acceleration with a minimum cost. Duration of the project can be accelerated by 12 days at a total cost increase of Rp 1,860,544.25. Generated a total duration of 19 days and the total cost of Rp 139,978,865.53. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
Scheduling plays a very important role in a construction project. Each project has a duration that is determined from a variety of considerations. Schedule is a very useful tool to explain the activities required in the completion of a project. The ultimate goal is for the project to be completed on time and economically. <br />
<br />
<br />
ITB builds Labtek I and GKU II buildings in Jatinangor. Schedule plans both buildings began on June 23rd, 2012 and will be completed on December 23rd, 2012. However, due to various issues, the project has been delayed. Delay in the project could result in financial loss to the owner as well as the contractor, so the contractor should make up the delays by speeding up project activities on the critical path by adding more labors, tools, method change, material change, etc. This is called a crash program. <br />
<br />
<br />
One of crash program that is implemented by the contractor is on the wall construction. Alternative methods of crashing that can be done are replacing wall material, adding labors, and adding the work hours. <br />
<br />
<br />
From the analysis conducted found that doing a crash program by replacing the common red brick to lightweight brick on the GKU II’s first floor wall work, produces an acceleration with a minimum cost. Duration of the project can be accelerated by 12 days at a total cost increase of Rp 1,860,544.25. Generated a total duration of 19 days and the total cost of Rp 139,978,865.53. |
format |
Final Project |
author |
TERTIYANTONO (NIM : 15008042), SENO |
spellingShingle |
TERTIYANTONO (NIM : 15008042), SENO CRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR |
author_facet |
TERTIYANTONO (NIM : 15008042), SENO |
author_sort |
TERTIYANTONO (NIM : 15008042), SENO |
title |
CRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR |
title_short |
CRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR |
title_full |
CRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR |
title_fullStr |
CRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR |
title_full_unstemmed |
CRASH PROGRAM ANALYSIS OF WALL WORK ON CONSTRUCTION PROJECT OF GEDUNG KULIAH UMUM II IN CAMPUS OF ITB JATINANGOR |
title_sort |
crash program analysis of wall work on construction project of gedung kuliah umum ii in campus of itb jatinangor |
url |
https://digilib.itb.ac.id/gdl/view/24259 |
_version_ |
1821840821814558720 |