IMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA
PT Freeport Indonesia, a subsidiary of Freeport McMoran Inc. applied two method of mine, which are open pit mine <br /> <br /> and underground mine. PT Freeport Indonesia expected the Grasberg mine, as open pit mine, will decline around <br /> <br /> 2017/2018 and following i...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/24408 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:24408 |
---|---|
spelling |
id-itb.:244082017-10-02T15:56:52ZIMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA SURYA ATMAJA TRIJAYA SITORUS 29115288, SUHARTO Indonesia Theses INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/24408 PT Freeport Indonesia, a subsidiary of Freeport McMoran Inc. applied two method of mine, which are open pit mine <br /> <br /> and underground mine. PT Freeport Indonesia expected the Grasberg mine, as open pit mine, will decline around <br /> <br /> 2017/2018 and following increase of DLMZ and GBC mine as underground mine. Therefore, PT Freeport Indonesia <br /> <br /> need high physical availability of equipment to accelerate future underground mine. The changes of operational model <br /> <br /> will affected the changes of commodity and type of equipment requirement. It will then lead to changes of inventory <br /> <br /> stock item. Obviously high availability of equipment also need high availability of materials, which reflected in service <br /> <br /> level indicator. Unfortunately, Supply Chain Division possess current Service Level below 78%, and need to increase <br /> <br /> the Service Level at minimum 78% per corporate target. <br /> <br /> There are two identified supply processes in this thesis that affected service level, which are internal supply factor and <br /> <br /> external supply factor. This research will focus to analyze problem in internal supply factor, which consist of <br /> <br /> warehouse issuing process, user demand characteristic, safety stock strategy, and onsite lead-time. This thesis will use <br /> <br /> operating spares inventory with fast and superfast item, because 69% of inventory value under operating spares <br /> <br /> category, and considering only 8% of operating spares are fast and superfast item that possess low service level. From <br /> <br /> internal supply factors, the main causes are identified, which are late warehouse issuing process, demand exceeding <br /> <br /> stocking plan, long onsite lead time, same/next day requirement date, and wrong issuing. The issue tree diagram <br /> <br /> develop to identify root causes that contribute to main causes. <br /> <br /> To improve supply process, DMAIC method will use to solve the root causes. The reason is six sigma as management <br /> <br /> strategy for improving product and process quality, and have been evolve from focusing in metric, to the methodology <br /> <br /> level and finally to design of entire management system. By analyze current business practice from standard procedure <br /> <br /> and policy, and conduct focus group discussion among leadership in warehouse, inventory, and customer, the <br /> <br /> researcher then develop alternative business solution. The alternative business solution will map into five categories <br /> <br /> initiative, which are people, process, communication, technology and management. The expected benefit from <br /> <br /> improvement process are increasing service level into 86%, contribute from improvement issuing process (14.9%), <br /> <br /> safety stock strategy (15.6%), demand characteristic (9.5%), reducing wrong issued (7%), and onsite lead-time (1.3%), <br /> <br /> and reducing inventory value that contribute from reducing cancelation of reservation monthly average around USD <br /> <br /> 1.13 million, and onsite lead time around USD 13.62 million. <br /> <br /> The implementation plan will divide into three period, which are short term (less than six month), medium term (six <br /> <br /> month to one year) and long term (over than one year until three year). The initiative cost also calculate which are <br /> <br /> majority cost come from installation and high density racking & build new storage facility to accommodate increasing <br /> <br /> availability of stock. <br /> text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
PT Freeport Indonesia, a subsidiary of Freeport McMoran Inc. applied two method of mine, which are open pit mine <br />
<br />
and underground mine. PT Freeport Indonesia expected the Grasberg mine, as open pit mine, will decline around <br />
<br />
2017/2018 and following increase of DLMZ and GBC mine as underground mine. Therefore, PT Freeport Indonesia <br />
<br />
need high physical availability of equipment to accelerate future underground mine. The changes of operational model <br />
<br />
will affected the changes of commodity and type of equipment requirement. It will then lead to changes of inventory <br />
<br />
stock item. Obviously high availability of equipment also need high availability of materials, which reflected in service <br />
<br />
level indicator. Unfortunately, Supply Chain Division possess current Service Level below 78%, and need to increase <br />
<br />
the Service Level at minimum 78% per corporate target. <br />
<br />
There are two identified supply processes in this thesis that affected service level, which are internal supply factor and <br />
<br />
external supply factor. This research will focus to analyze problem in internal supply factor, which consist of <br />
<br />
warehouse issuing process, user demand characteristic, safety stock strategy, and onsite lead-time. This thesis will use <br />
<br />
operating spares inventory with fast and superfast item, because 69% of inventory value under operating spares <br />
<br />
category, and considering only 8% of operating spares are fast and superfast item that possess low service level. From <br />
<br />
internal supply factors, the main causes are identified, which are late warehouse issuing process, demand exceeding <br />
<br />
stocking plan, long onsite lead time, same/next day requirement date, and wrong issuing. The issue tree diagram <br />
<br />
develop to identify root causes that contribute to main causes. <br />
<br />
To improve supply process, DMAIC method will use to solve the root causes. The reason is six sigma as management <br />
<br />
strategy for improving product and process quality, and have been evolve from focusing in metric, to the methodology <br />
<br />
level and finally to design of entire management system. By analyze current business practice from standard procedure <br />
<br />
and policy, and conduct focus group discussion among leadership in warehouse, inventory, and customer, the <br />
<br />
researcher then develop alternative business solution. The alternative business solution will map into five categories <br />
<br />
initiative, which are people, process, communication, technology and management. The expected benefit from <br />
<br />
improvement process are increasing service level into 86%, contribute from improvement issuing process (14.9%), <br />
<br />
safety stock strategy (15.6%), demand characteristic (9.5%), reducing wrong issued (7%), and onsite lead-time (1.3%), <br />
<br />
and reducing inventory value that contribute from reducing cancelation of reservation monthly average around USD <br />
<br />
1.13 million, and onsite lead time around USD 13.62 million. <br />
<br />
The implementation plan will divide into three period, which are short term (less than six month), medium term (six <br />
<br />
month to one year) and long term (over than one year until three year). The initiative cost also calculate which are <br />
<br />
majority cost come from installation and high density racking & build new storage facility to accommodate increasing <br />
<br />
availability of stock. <br />
|
format |
Theses |
author |
SURYA ATMAJA TRIJAYA SITORUS 29115288, SUHARTO |
spellingShingle |
SURYA ATMAJA TRIJAYA SITORUS 29115288, SUHARTO IMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA |
author_facet |
SURYA ATMAJA TRIJAYA SITORUS 29115288, SUHARTO |
author_sort |
SURYA ATMAJA TRIJAYA SITORUS 29115288, SUHARTO |
title |
IMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA |
title_short |
IMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA |
title_full |
IMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA |
title_fullStr |
IMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA |
title_full_unstemmed |
IMPROVEMENT SUPPLY PROCESS TO INCREASE SERVICE LEVEL STUDY CASE SUPPLY CHAIN DIVISION PT FREEPORT INDONESIA |
title_sort |
improvement supply process to increase service level study case supply chain division pt freeport indonesia |
url |
https://digilib.itb.ac.id/gdl/view/24408 |
_version_ |
1822921215190237184 |