PENGEMBANGAN TPS CIBEUNYING MENJADI TPS TERINTEGRASI DI KOTA BANDUNG
Waste is one of the environmental problems that continuously happen in Indonesia. One of the methods to handle the waste generation is transfer station. Transfer station is used as a short-term storage of wastes before being transferred to landfill. One of transfer stations in Bandung City is Cib...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/36956 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | Waste is one of the environmental problems that continuously happen in
Indonesia. One of the methods to handle the waste generation is transfer station.
Transfer station is used as a short-term storage of wastes before being transferred
to landfill. One of transfer stations in Bandung City is Cibeunying transfer
station. Facilities and infrastructures of this transfer station were evaluated by
technical requirements from the Ministry of Public Works Regulation No. 03 Year
2013. The supporting data was waste sources data from served areas, dimension
of the building, the function and facilities of the building, waste composition, peak
hour of vehicle, and waste generation data of eight days in a row. In 2014, the
total consumer is 15,328 people with 0.52 kg/person/day or 10.67 tonnes/day for
its average waste generation. While the nonhousehold has 50 units in served and
generates 9.37 tonnes/day. This transfer station is dominated by 58.21% organic
waste, 15.60% paper & cardboard, and 7.40% plastic packaging for its waste
composition. Based on the evaluation, Cibeunying transfer station need to be
enhanced in several sectors. The development was done by determining design
concept and preliminary design to fulfil the capacity in the next ten years. The
concept was done by cutting the service area, waste generation prediction,
choosing the best scenario and applying new utilities such as expanding the area,
organizing the collection and transportation system, installing the leachate
storage, applying garden to give the aesthetics impression, adding new areas such
as unloading area, sorting, weighing and recording, and storage. Preliminary
design, as the second step of design, consists of criteria and specification of
design for each recommended alternatives including the layout and 3d perspective
drawing of new transfer station. |
---|