CONSTRUCTION MANAGEMENT ASPECTS PLANNING OF GEDUNG PUSAT SENI DAN BUDAYA BANDUNG
The Bandung Arts and Culture Center building located in the Jalan Laswi Bandung area is a building that functions as a theater and gallery. This final project will discuss planning and construction of the Center for Arts and Culture. The scope of this Final Project involves the creation of Work B...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/40171 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | The Bandung Arts and Culture Center building located in the Jalan Laswi Bandung area is a
building that functions as a theater and gallery. This final project will discuss planning and
construction of the Center for Arts and Culture. The scope of this Final Project involves the
creation of Work Breakdown Structures, planning of construction methods, work volume
calculations, project scheduling based on productivity, and project cost estimation. The scope
of work in this Final Project extends from preparatory work, geotechnical and lower structure
work, upper structure work, and transportation system work. Work volume is calculated
manually. Work duration is calculated based on heavy equipment lead resources and labor lead
resources. Cost estimation is calculated with both unit price method based on Permen PU No.
28/2016 and resource enumeration method. The duration of project work is 654 days which
are divided as follows. Preparatory work was carried out for 20 days, geotechnical and lower
structure work were carried out for 266 days, the upper structure work was carried out for 330
days, drainage work was carried out for 21 days and Transportation system works were carried
out for 11 days. This project budget plan is Rp.61,628,299,623 with a cost percentage of 0.92%
for preparatory work, 54.69% for geotechnical work and lower structure, 69.727% for
structural work, 3.20% for drainage work. And 1.56% for road works |
---|