EVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM
Road drainage channel and river that have bad condition as main problem that can cause flooding. Flood is very dangerous disaster because can loss of property, loss of life, and damage to infrastructure. One of the areas that is often hit by flooding is Rancaekek. The flood occoured around the Ra...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/44917 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:44917 |
---|---|
spelling |
id-itb.:449172019-11-13T10:30:19ZEVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM Sidik, Ahmad Teknik (Rekayasa, enjinering dan kegiatan berkaitan) Indonesia Final Project Road Drainage Channel, River, HEC-RAS, Changes In Cross-section. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/44917 Road drainage channel and river that have bad condition as main problem that can cause flooding. Flood is very dangerous disaster because can loss of property, loss of life, and damage to infrastructure. One of the areas that is often hit by flooding is Rancaekek. The flood occoured around the Rancaekek Highway be passed by two rivers, they are Cikijing River and Cimande River. This flood cause by road drainage channel in bad condition and overflow of Cikijing River and Cimande River. In December 2014 – January 2015 recorded that flood in area up to 1 – 1.5 meters. Based on analysis, planning of road drainage channel using discharge of 5 years return periode obtained 117.76 milimeters of rainfall and capacity evaluation of river using discharge of 25 years return periode obtained Cikijing River discharge 106.87 m3/s and Cimande River discharge 161.61 m3/s. From the comparison result of plan discharge with existing discharge of road drainage channel and river exist cross section that cannot accommodate plan discharge so giving overflow. Therefore, will be flood problem handling by changing the cross section. In case of surface water modelling will be used HEC-RAS 4.1.0 software. Based on the result of the calculation and modelling obtained the solution of best cross section change to stop the overflow. By using the alternative of the best of road drainage channel cross section and river in the order to solve flooding problem that happened in Rancaekek Highway. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Teknik (Rekayasa, enjinering dan kegiatan berkaitan) |
spellingShingle |
Teknik (Rekayasa, enjinering dan kegiatan berkaitan) Sidik, Ahmad EVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM |
description |
Road drainage channel and river that have bad condition as main problem that can
cause flooding. Flood is very dangerous disaster because can loss of property, loss
of life, and damage to infrastructure. One of the areas that is often hit by flooding
is Rancaekek. The flood occoured around the Rancaekek Highway be passed by
two rivers, they are Cikijing River and Cimande River. This flood cause by road
drainage channel in bad condition and overflow of Cikijing River and Cimande
River. In December 2014 – January 2015 recorded that flood in area up to 1 – 1.5
meters.
Based on analysis, planning of road drainage channel using discharge of 5 years
return periode obtained 117.76 milimeters of rainfall and capacity evaluation of
river using discharge of 25 years return periode obtained Cikijing River discharge
106.87 m3/s and Cimande River discharge 161.61 m3/s. From the comparison
result of plan discharge with existing discharge of road drainage channel and river
exist cross section that cannot accommodate plan discharge so giving overflow.
Therefore, will be flood problem handling by changing the cross section.
In case of surface water modelling will be used HEC-RAS 4.1.0 software. Based
on the result of the calculation and modelling obtained the solution of best cross
section change to stop the overflow. By using the alternative of the best of road
drainage channel cross section and river in the order to solve flooding problem
that happened in Rancaekek Highway. |
format |
Final Project |
author |
Sidik, Ahmad |
author_facet |
Sidik, Ahmad |
author_sort |
Sidik, Ahmad |
title |
EVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM |
title_short |
EVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM |
title_full |
EVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM |
title_fullStr |
EVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM |
title_full_unstemmed |
EVALUATION AND REDESIGN ROAD DRAINAGE CHANNEL AND RIVER ON RANCAEKEK HIGHWAY AS SOLUTION ALTERNATIVE OF FLOOD PROBLEM |
title_sort |
evaluation and redesign road drainage channel and river on rancaekek highway as solution alternative of flood problem |
url |
https://digilib.itb.ac.id/gdl/view/44917 |
_version_ |
1821999236384817152 |