CONSTRUCTION MANAGEMENT ASPECTS PLANNING OF MIXEDUSE BUILDING âCIBADAK BUILDINGâ, ASTANA ANYAR, BANDUNG
Cibadak Building is a mixed-use building that functions as an apartment and commercial area with additional entertainment facilities. This building is needed to increase various economic activities simultaneously. This final project discusses the planning aspects of construction management in the...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/51479 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | Cibadak Building is a mixed-use building that functions as an apartment and
commercial area with additional entertainment facilities. This building is needed
to increase various economic activities simultaneously. This final project discusses
the planning aspects of construction management in the construction of the Cibadak
Building. This building consists of 2 basemen floors, 4 podium floors and 7
apartment floors. In general, the scope of this Final Project includes breaking down
Work Breakdown Structures, planning implementation methods that include site
plans and zoning, quantifying take-off, determining scheduling based on
productivity, and estimating project costs in detail. The construction method is
planned by dividing it into work packages. Determination of the duration of work
is carried out based on two factors, namely based on lead resources for heavy
equipment and lead resources for labor. Detailed cost estimates are carried out
with a unit price based on SNI and Permen PU No. 28 of 2016 and resource
enumeration. The total duration of construction of this project is 556 days starting
January 10, 2022 to October 19, 2023. Preparatory work is carried out for 41 days,
substructure work for 118 days, superstructure work for 405 days, drainage work
for 5 days and pavement work for 9 days. The cost estimation process resulted in
the project's Budget Plan (RAB) of Rp. 137,973,639,022.
|
---|