TECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE
PT XYZ is a contractor company engaged in the mining industry. The company was asked to work on a mining project in the highlands of Mimika Regency, Papua Province, as material for dam construction. The dam is located in the lowlands on the west and east sides of the Ajkwa River. The materials ne...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/51630 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:51630 |
---|---|
spelling |
id-itb.:516302020-09-29T16:38:52ZTECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE Candra Pratama P, Charles Pertambangan dan operasi berkaitan Indonesia Final Project mine design, quarry, mine scheduling, excavator, hauling truck INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/51630 PT XYZ is a contractor company engaged in the mining industry. The company was asked to work on a mining project in the highlands of Mimika Regency, Papua Province, as material for dam construction. The dam is located in the lowlands on the west and east sides of the Ajkwa River. The materials needed for dam construction are gravel and boulder of alluvium lithology (Qa) which are available as resources. To meet the material needs for the dam construction, it is necessary to design and plan the mining of the materials that will be transported to material storage location Run of Mine (ROM) and stockpile. Research will be carried out related to the design of the open quarry mining method using shovel and trucks and calculating the annual production that will be required in the construction. Based on the results of the quarry design, 14 quarries were found in 5 different resource locations, namely Kalikopi, Borrow East, Borrow West, NEL, and NEL Extended with total mining reserves of 106.3 million m3. The average annual output reaches 5 million m3/ year. In addition, to achieve the production target, research is also carried out related to determining the need for digger equipment and hauler equipment. Digger equipment using excavators Backhoe Komatsu PC750 with averaged six (6) units per year. Hauler equipment using dumptruck Hino FM 260 JD with average four (4) units in one fleet or an average of 24 units per year. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Pertambangan dan operasi berkaitan |
spellingShingle |
Pertambangan dan operasi berkaitan Candra Pratama P, Charles TECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE |
description |
PT XYZ is a contractor company engaged in the mining industry. The company was asked to
work on a mining project in the highlands of Mimika Regency, Papua Province, as material
for dam construction. The dam is located in the lowlands on the west and east sides of the
Ajkwa River. The materials needed for dam construction are gravel and boulder of alluvium
lithology (Qa) which are available as resources. To meet the material needs for the dam
construction, it is necessary to design and plan the mining of the materials that will be
transported to material storage location Run of Mine (ROM) and stockpile. Research will be
carried out related to the design of the open quarry mining method using shovel and trucks and
calculating the annual production that will be required in the construction. Based on the results
of the quarry design, 14 quarries were found in 5 different resource locations, namely Kalikopi,
Borrow East, Borrow West, NEL, and NEL Extended with total mining reserves of 106.3
million m3. The average annual output reaches 5 million m3/ year. In addition, to achieve the
production target, research is also carried out related to determining the need for digger
equipment and hauler equipment. Digger equipment using excavators Backhoe Komatsu
PC750 with averaged six (6) units per year. Hauler equipment using dumptruck Hino FM 260
JD with average four (4) units in one fleet or an average of 24 units per year. |
format |
Final Project |
author |
Candra Pratama P, Charles |
author_facet |
Candra Pratama P, Charles |
author_sort |
Candra Pratama P, Charles |
title |
TECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE |
title_short |
TECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE |
title_full |
TECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE |
title_fullStr |
TECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE |
title_full_unstemmed |
TECHNICAL DESIGN OF MINING CONSTRUCTION DAM MATERIALS IN PT XYZ, MIMIKA DISTRICT, PAPUA PROVINCE |
title_sort |
technical design of mining construction dam materials in pt xyz, mimika district, papua province |
url |
https://digilib.itb.ac.id/gdl/view/51630 |
_version_ |
1822001011299975168 |