STRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK
Asset and site restoration become a critical process for any oil and gas exploration and exploitation operation. It is a mandatory for any production operator to ensure the ex-location of an oil or gas well are fully recovered as environmental-friendly habitat. One of the initial process of the...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/53548 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:53548 |
---|---|
spelling |
id-itb.:535482021-03-06T18:20:26ZSTRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK Budi Utomo, Santoso Manajemen umum Indonesia Theses Oil and Gas, Drilling and Completion, Plug and Abandon, Decommissioning, Barrier, Subsurface Integrity, Brainstorming, Why Tree Analysis, Analytic Hierarchy Process, Rig, Coil Tubing Unit, Cycle Time. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/53548 Asset and site restoration become a critical process for any oil and gas exploration and exploitation operation. It is a mandatory for any production operator to ensure the ex-location of an oil or gas well are fully recovered as environmental-friendly habitat. One of the initial process of the asset and site restoration is well’s subsurface plug and abandonment operation. The main objective of subsurface plug and abandonment operation is to set a mechanical barrier (cement plugs) inside and outside wellbore to ensure sealing between each hydrocarbon zones and between hydrocarbon zones to surface. During the last 3 years, PT. Pacific Oil Company ( not a real name) has been actively conducted plug and abandonment projects as per government rules and regulations. The challenge came in lately for 2019 plug and abandonment project. There was a long discussion on the project approval process because the government decided not to extend the permit for the company to continue operate the concession block. After those long discussion and approval process, the project was approved to be executed in 2020. Then another challenge came to complete the project in a shorter duration due to handover process from the company to the new operator. In the previous years, the duration of the project was about 9-10 months. For this project, the company management gave the target to complete the project less than 7 months. The project team conduct a brainstorm session to gather any ideas how to achieve the management direction. The project team used conceptual framework of why tree analysis and conducted a thorough review to generates the possible alternatives. By conducting a brainstorm session in the team meeting and discussion, there are 5 major elements that may have impact to the project schedule: work program/procedures, organization capability, tools and services, well’s equipment and materials, and environmental. Based on several focus group discussions, it is concluded that the most significant and direct impact on accelerating the plug and abandonment project is by adding new unit to execute the project. To add a new unit, the project team select 3 (three) possible alternatives: Add new rig, Reallocate workover/well service rig, combine rig and coil tubing unit. There were 3 (three) decision criteria for this process: Project schedule uncertainty, Impact to production, Total cost of action. Then the project team used analytic hierarchy process to compare each alternative and calculate 2 the best alternative for the project execution. The final calculated scores are Add new rig (0.339), Re-allocate workover/well service rig (0.292), combine rig and coil tubing unit (0.369). Based on the final calculated score, the selected alternative was using a combination of rig and coil tubing unit to execute plug and abandonment project. The proposed alternative will require low efforts to achieve the project schedule target but maintaining the production target and keep the total cost under budget. It was proven that the combination of rig and coil tubing unit can accelerate the completion of plug and abandonment project. During the implementation period, the project team conducted verification and validation of the decision. It was found that there was a challenging issue on the scheduling strategy, especially on the location preparation. So, the schedule was mixed between the normal wells and the hybrid wells, whichever location ready first. However, the overall result was good for the company. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Manajemen umum |
spellingShingle |
Manajemen umum Budi Utomo, Santoso STRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK |
description |
Asset and site restoration become a critical process for any oil and gas exploration and
exploitation operation. It is a mandatory for any production operator to ensure the ex-location of
an oil or gas well are fully recovered as environmental-friendly habitat. One of the initial process
of the asset and site restoration is well’s subsurface plug and abandonment operation. The main
objective of subsurface plug and abandonment operation is to set a mechanical barrier (cement
plugs) inside and outside wellbore to ensure sealing between each hydrocarbon zones and between
hydrocarbon zones to surface. During the last 3 years, PT. Pacific Oil Company ( not a real name)
has been actively conducted plug and abandonment projects as per government rules and
regulations. The challenge came in lately for 2019 plug and abandonment project. There was a
long discussion on the project approval process because the government decided not to extend the
permit for the company to continue operate the concession block. After those long discussion and
approval process, the project was approved to be executed in 2020. Then another challenge came
to complete the project in a shorter duration due to handover process from the company to the new
operator. In the previous years, the duration of the project was about 9-10 months. For this project,
the company management gave the target to complete the project less than 7 months.
The project team conduct a brainstorm session to gather any ideas how to achieve the
management direction. The project team used conceptual framework of why tree analysis and
conducted a thorough review to generates the possible alternatives. By conducting a brainstorm
session in the team meeting and discussion, there are 5 major elements that may have impact to
the project schedule: work program/procedures, organization capability, tools and services, well’s
equipment and materials, and environmental. Based on several focus group discussions, it is
concluded that the most significant and direct impact on accelerating the plug and abandonment
project is by adding new unit to execute the project.
To add a new unit, the project team select 3 (three) possible alternatives: Add new rig, Reallocate
workover/well
service
rig,
combine
rig
and
coil
tubing
unit.
There
were
3
(three)
decision
criteria
for this process: Project schedule uncertainty, Impact to production, Total cost of action.
Then the project team used analytic hierarchy process to compare each alternative and calculate
2
the best alternative for the project execution. The final calculated scores are Add new rig (0.339),
Re-allocate workover/well service rig (0.292), combine rig and coil tubing unit (0.369).
Based on the final calculated score, the selected alternative was using a combination of rig
and coil tubing unit to execute plug and abandonment project. The proposed alternative will require
low efforts to achieve the project schedule target but maintaining the production target and keep
the total cost under budget. It was proven that the combination of rig and coil tubing unit can
accelerate the completion of plug and abandonment project. During the implementation period,
the project team conducted verification and validation of the decision. It was found that there was
a challenging issue on the scheduling strategy, especially on the location preparation. So, the
schedule was mixed between the normal wells and the hybrid wells, whichever location ready first.
However, the overall result was good for the company. |
format |
Theses |
author |
Budi Utomo, Santoso |
author_facet |
Budi Utomo, Santoso |
author_sort |
Budi Utomo, Santoso |
title |
STRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK |
title_short |
STRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK |
title_full |
STRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK |
title_fullStr |
STRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK |
title_full_unstemmed |
STRATEGIC DECISION ANALYSIS TO ACCELERATE PLUG & ABANDONMENT PROJECT AT SUMATRA BLOCK |
title_sort |
strategic decision analysis to accelerate plug & abandonment project at sumatra block |
url |
https://digilib.itb.ac.id/gdl/view/53548 |
_version_ |
1822929359459057664 |