DECISION ANALYSIS FOR CLEANING METHOD SELECTION OF 26â HCT SHIPPING LINE
Many Oil and Gas companies are taking various efficiency and optimization measures to remain competitive to stay in business. One of the efficiency measures is to ensure that every facility that is no longer used for operation can be carried out by dismantling the facility to reduce maintenance c...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/55025 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | Many Oil and Gas companies are taking various efficiency and optimization measures to remain
competitive to stay in business. One of the efficiency measures is to ensure that every facility that
is no longer used for operation can be carried out by dismantling the facility to reduce
maintenance cost, inspection costs and minimize pipe damage and leakage due to decreased
pipeline integrity/strength and potential vandalism of the facility.
HCT 26" pipe owned by PT CPI, has experiences leakage problems, significant thinning of the
pipe thickness which can lead to environmental pollution of the soil and potential hazards to
residents around the pipeline. With the decision of the CPI leadership that the pipeline was no
longer used to support the operations of PT. CPI, a comprehensive analysis is needed to clean the
remaining crude oil inside the pipeline
This final project aims to formulate a solution as well as a recommendation from the proposed
alternative cleaning identified in the pipeline owned by PT. CPI. The result of this final project
is the selection of alternatives which are considered as optimal solutions from several identified
alternatives.
Pipe condition problems were evaluated using the Kepner-Tregoe (KT) Situation Appraisal. The
root of the pipeline condition and safety problem is then analyzed using the KT - problem analysis
and verified using the 5 whys method. In obtaining alternatives that have the potential as a
solution to the existing problems, the Value Focused Thinking (VFT) method is used. Then the
alternative selection process uses the Simple Multi Attribute Rating Technique (SMART)
method. Qualitative analysis for pairwise comparisons is carried out through group discussions
of four people who have deep knowledge and experience of piping engineering, project
management, construction and operations. The results of the analysis are then submitted to the
chief decision maker.
The alternative proposed to solve this problem is to clean the pipeline using the Deoiling method.
The results of this research will then be proposed to be a project that will be implemented using
the concept of project management. |
---|