MINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE
During mining operations, pits will be formed in the form of basins then water enters the pit basin and causes a muddy mining front. Construction of drainage facilities in the form of ditches, sumps, and pumping systems will facilitate water removal from the pits. The installation of settling pon...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/61976 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:61976 |
---|---|
spelling |
id-itb.:619762021-09-29T08:35:42ZMINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE Muhammad, Zaki Indonesia Final Project Drainage facilities, Open channels, Drop structure, Sump, Pump, Retention pond, Settling pond. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/61976 During mining operations, pits will be formed in the form of basins then water enters the pit basin and causes a muddy mining front. Construction of drainage facilities in the form of ditches, sumps, and pumping systems will facilitate water removal from the pits. The installation of settling ponds is also required as one of the conditions that must be met by mining companies to maintain the water quality standards. This research starts with the analysis of rain data from Rain Measurement Station 2 for the data period 2013-2021 using the Pearson III Log distribution, the rainfall was 118.66 mm with the rainfall intensity in the 10-year return period was 25.91 mm/hour. From the topographic data and the mine plan scheduling data, catchment areas are made. In PT XYZ's Semeru Wastedump, the total catchment area of 3.3 km² is divided into 54 sub-catchments with varying values. The open channel is divided into 4 (four) categories which are divided into 3 (three) categories for the main channel with dimensions of width x height of 2.77 x 1.2 m; 4 x 1m; 5 x 1.5 and 1 (one) category for the channel on the bench (ditch) with dimensions of width x height of 2.77 x 1.2 m. Drop structures are made for steep pit slopes of 3 (three) for the period 2020-2021, 2 (two) for the period 2022-2023, and 3 (three) for the period 2024-2026. Mine sump dewatering (in the period 2020- 2021) will be pumped using Multiflo 290 of 1 (one) unit with the option of the sump being dried after 4 (four) days. Installation of 4 (four) retention ponds and 6 (six) settling ponds for the period 2020-2023 and 4 (four) retention ponds and 5 (five) settling ponds for the period 2023-2030 with varying retention pond dimensions and same dimensions for all of the settling ponds. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
During mining operations, pits will be formed in the form of basins then water
enters the pit basin and causes a muddy mining front. Construction of drainage
facilities in the form of ditches, sumps, and pumping systems will facilitate water
removal from the pits. The installation of settling ponds is also required as one of
the conditions that must be met by mining companies to maintain the water quality
standards.
This research starts with the analysis of rain data from Rain Measurement Station
2 for the data period 2013-2021 using the Pearson III Log distribution, the rainfall
was 118.66 mm with the rainfall intensity in the 10-year return period was 25.91
mm/hour. From the topographic data and the mine plan scheduling data, catchment
areas are made. In PT XYZ's Semeru Wastedump, the total catchment area of 3.3
km² is divided into 54 sub-catchments with varying values.
The open channel is divided into 4 (four) categories which are divided into 3 (three)
categories for the main channel with dimensions of width x height of 2.77 x 1.2 m;
4 x 1m; 5 x 1.5 and 1 (one) category for the channel on the bench (ditch) with
dimensions of width x height of 2.77 x 1.2 m. Drop structures are made for steep
pit slopes of 3 (three) for the period 2020-2021, 2 (two) for the period 2022-2023,
and 3 (three) for the period 2024-2026. Mine sump dewatering (in the period 2020-
2021) will be pumped using Multiflo 290 of 1 (one) unit with the option of the sump
being dried after 4 (four) days. Installation of 4 (four) retention ponds and 6 (six)
settling ponds for the period 2020-2023 and 4 (four) retention ponds and 5 (five)
settling ponds for the period 2023-2030 with varying retention pond dimensions
and same dimensions for all of the settling ponds. |
format |
Final Project |
author |
Muhammad, Zaki |
spellingShingle |
Muhammad, Zaki MINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE |
author_facet |
Muhammad, Zaki |
author_sort |
Muhammad, Zaki |
title |
MINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE |
title_short |
MINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE |
title_full |
MINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE |
title_fullStr |
MINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE |
title_full_unstemmed |
MINE DRAINAGE FACILITY PLANNING OF SEMERU WASTE DUMP AT PT XYZ COAL MINE |
title_sort |
mine drainage facility planning of semeru waste dump at pt xyz coal mine |
url |
https://digilib.itb.ac.id/gdl/view/61976 |
_version_ |
1822003980439388160 |