LEMBAR PENGESAHAN TUGAS SARJANA DENGAN JUDUL: RANCANGAN PERBAIKAN PROSES PRODUKSI COAL NOZZLE BURNER DENGAN PENDEKATAN LEAN MANUFACTURING
PT PLN (Persero) Pusharlis UP2W VI Surabaya produces coal nozzle burner components using make to order system. Every year, the company strives to continuously improve its performance by focused on the timeliness of production. In the last three years, the average timeliness of production for the...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/63880 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | PT PLN (Persero) Pusharlis UP2W VI Surabaya produces coal nozzle burner
components using make to order system. Every year, the company strives to
continuously improve its performance by focused on the timeliness of production.
In the last three years, the average timeliness of production for the coal nozzle
burner is 93% of the 100% target. Some delay cases that still happened were caused
by several waste along the production line which will extend production lead time.
Lean manufacturing approach is used to analyze waste that occurs along the
production line. This study will take further waste analysis using Waste-Failure
Mode and Effect Analysis (W-FMEA) to determine the level of waste reduction
based on the critical causes. Then, some alternative improvements will be choosen
based on level of waste reduction to eliminate or minimize waste. The selected
improvements are including making SOP for handling defect materials and
products, providing training and certification of workers, and also optimizing the
implementation of 5S. The final result shows a plan that is capable to reduce the
production lead time from 7672,75 minutes to 5889,76 minutes, and reduce non-
value added activity (NVA) by 27,69%.
|
---|