A FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD
Indonesia's rank in global competitiveness is 50th out of 141 countries. Infrastructure development is a key to this competitiveness. The construction of the Trans Sumatera Toll Road is one of the Government of Indonesia’s (GOI) focus to improve the Indonesian economy by reducing the cost of...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/63988 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:63988 |
---|---|
spelling |
id-itb.:639882022-03-25T11:10:50ZA FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD Aria Permana, Deny Manajemen umum Indonesia Theses financial feasibility, economic feasibility, Net Present Value, IRR, Payback period, vehicle operating cost, vehicle operating time INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/63988 Indonesia's rank in global competitiveness is 50th out of 141 countries. Infrastructure development is a key to this competitiveness. The construction of the Trans Sumatera Toll Road is one of the Government of Indonesia’s (GOI) focus to improve the Indonesian economy by reducing the cost of transporting goods and logistics between Java and Sumatera. PT Hutama Karya (Persero) has been appointed by the GOI to carry out the task of constructing the Trans Sumatera Toll Road, one of which is the 207 Km Rengat – Pekanbaru segment. This final project will focus conducting a financial feasibility study and an economic feasibility study of the Rengat – Pekanbaru segment of the Trans Sumatera Toll Road. The financial feasibility study considers the potential operating cash flows of the toll road from traffic and from toll rates, while the economic feasibility study considers the potential benefits that will be received to the community on two sides, saving from Vehicle Operating Cost and saving in Vehicle Operating Time. Based on the financial feasibility study, the Rengat – Pekanbaru segment of the Trans Sumatera Toll Road is not feasible to be implemented because it has IRR = 3.23% which is lower than the discount rate of 11.6%, NPV = Rp. (31,058,356.015) and Payback period of more than 40 years (exceeding concession period). Based on the economic feasibility study, the Rengat – Pekanbaru segment of the Trans Sumatera Toll Road is feasible to be implemented because it has a Vehicle Operating Cost Saving (VOCS) of Rp.34,518,789,566 (best case), a VOCS of Rp.28,820,764,540 (base case), and a VOCS of Rp. 19,285,489,206 (worst case). The Rengat – Pekanbaru segment of the Trans Sumatera Toll Road has a Vehicle Operating Time Saving (VOTS) of 2.02 hours (best case), 1.53 hours (base case) and 0.84 hours (worst case). This is why the GOI took a policy to continue carrying out the construction of the Rengat – Pekanbaru segment of the Trans Sumatera Toll Road with an assignment to Hutama Karya. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Manajemen umum |
spellingShingle |
Manajemen umum Aria Permana, Deny A FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD |
description |
Indonesia's rank in global competitiveness is 50th out of 141 countries.
Infrastructure development is a key to this competitiveness. The construction of the
Trans Sumatera Toll Road is one of the Government of Indonesia’s (GOI) focus to
improve the Indonesian economy by reducing the cost of transporting goods and
logistics between Java and Sumatera. PT Hutama Karya (Persero) has been
appointed by the GOI to carry out the task of constructing the Trans Sumatera Toll
Road, one of which is the 207 Km Rengat – Pekanbaru segment.
This final project will focus conducting a financial feasibility study and an
economic feasibility study of the Rengat – Pekanbaru segment of the Trans
Sumatera Toll Road.
The financial feasibility study considers the potential operating cash flows of the
toll road from traffic and from toll rates, while the economic feasibility study
considers the potential benefits that will be received to the community on two sides,
saving from Vehicle Operating Cost and saving in Vehicle Operating Time.
Based on the financial feasibility study, the Rengat – Pekanbaru segment of the
Trans Sumatera Toll Road is not feasible to be implemented because it has IRR =
3.23% which is lower than the discount rate of 11.6%, NPV = Rp. (31,058,356.015)
and Payback period of more than 40 years (exceeding concession period).
Based on the economic feasibility study, the Rengat – Pekanbaru segment of the
Trans Sumatera Toll Road is feasible to be implemented because it has a Vehicle
Operating Cost Saving (VOCS) of Rp.34,518,789,566 (best case), a VOCS of
Rp.28,820,764,540 (base case), and a VOCS of Rp. 19,285,489,206 (worst case).
The Rengat – Pekanbaru segment of the Trans Sumatera Toll Road has a Vehicle
Operating Time Saving (VOTS) of 2.02 hours (best case), 1.53 hours (base case)
and 0.84 hours (worst case).
This is why the GOI took a policy to continue carrying out the construction of the
Rengat – Pekanbaru segment of the Trans Sumatera Toll Road with an assignment
to Hutama Karya. |
format |
Theses |
author |
Aria Permana, Deny |
author_facet |
Aria Permana, Deny |
author_sort |
Aria Permana, Deny |
title |
A FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD |
title_short |
A FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD |
title_full |
A FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD |
title_fullStr |
A FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD |
title_full_unstemmed |
A FINANCIAL AND ECONOMIC FEASIBILITY STUDY ON CONSTRUCTION OF THE RENGAT - PEKANBARU SEGMENT OF THE TRANS SUMATERA TOLL ROAD |
title_sort |
financial and economic feasibility study on construction of the rengat - pekanbaru segment of the trans sumatera toll road |
url |
https://digilib.itb.ac.id/gdl/view/63988 |
_version_ |
1822004440604868608 |