ALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE
Pidekso Dam is one of the dams in Wonogiri Regency, Central Java Province with a watershed area of 56.79 km2 which is projected to meet irrigation and raw water needs. One of the construction processes of the Pidekso Dam is the process of circumventing the river with a conduit diversion tunnel an...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/66464 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:66464 |
---|---|
spelling |
id-itb.:664642022-06-28T11:53:16ZALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE Iqbal Huseiny, Moh. Indonesia Final Project dam, diversion tunnel, cofferdam INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/66464 Pidekso Dam is one of the dams in Wonogiri Regency, Central Java Province with a watershed area of 56.79 km2 which is projected to meet irrigation and raw water needs. One of the construction processes of the Pidekso Dam is the process of circumventing the river with a conduit diversion tunnel and a cofferdam. The capacity of the original design of the conduit amounted to only 17.6% of the planned flood discharge. In addition, the dimensions of the original conduit are 1- hole horseshoe-shaped which has the potential to completely close the flow of water downstream when plugging the conduit. Therefore, an alternative building design planning is needed by adjusting the actual conditions in the field. Re-planning includes hydrological analysis based on the technical manual of flood discharge on dams and hydraulic analysis of the conduit with the help of HY-8 software. From the calculation results, an alternative dimension of the plan is a double box culvert measuring 3 m x 3 m x 2 holes with a maximum outflow discharge of 152.92 m3/s with maximum flood elevation at +171.32 m. The reinforcement used on the conduit is D25-200 on the upper slab, D19-150 on the side slab, D25-150 on the bottom slab, and D16-150 for shrinkage/divider reinforcement. The dimensions of the cofferdam were selected zonal type of inclined core with a slope of 1:3 and the summit elevation of the cofferdam was at +173 m. The budget cost for the building is about IDR 64 billion. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
Pidekso Dam is one of the dams in Wonogiri Regency, Central Java Province with
a watershed area of 56.79 km2 which is projected to meet irrigation and raw water
needs. One of the construction processes of the Pidekso Dam is the process of
circumventing the river with a conduit diversion tunnel and a cofferdam. The
capacity of the original design of the conduit amounted to only 17.6% of the
planned flood discharge. In addition, the dimensions of the original conduit are 1-
hole horseshoe-shaped which has the potential to completely close the flow of water
downstream when plugging the conduit. Therefore, an alternative building design
planning is needed by adjusting the actual conditions in the field. Re-planning
includes hydrological analysis based on the technical manual of flood discharge on
dams and hydraulic analysis of the conduit with the help of HY-8 software. From
the calculation results, an alternative dimension of the plan is a double box culvert
measuring 3 m x 3 m x 2 holes with a maximum outflow discharge of 152.92 m3/s
with maximum flood elevation at +171.32 m. The reinforcement used on the conduit
is D25-200 on the upper slab, D19-150 on the side slab, D25-150 on the bottom
slab, and D16-150 for shrinkage/divider reinforcement. The dimensions of the
cofferdam were selected zonal type of inclined core with a slope of 1:3 and the
summit elevation of the cofferdam was at +173 m. The budget cost for the building
is about IDR 64 billion. |
format |
Final Project |
author |
Iqbal Huseiny, Moh. |
spellingShingle |
Iqbal Huseiny, Moh. ALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE |
author_facet |
Iqbal Huseiny, Moh. |
author_sort |
Iqbal Huseiny, Moh. |
title |
ALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE |
title_short |
ALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE |
title_full |
ALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE |
title_fullStr |
ALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE |
title_full_unstemmed |
ALTERNATIVE DESIGN OF PIDEKSO DAM DIVERSION TUNNEL, WONOGIRI REGENCY, CENTRAL JAVA PROVINCE |
title_sort |
alternative design of pidekso dam diversion tunnel, wonogiri regency, central java province |
url |
https://digilib.itb.ac.id/gdl/view/66464 |
_version_ |
1822005163923079168 |