DECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP
PT Pertamina EP (PEP) as a subsidiary of Upstream Holding Pertamina has a role to carry out exploration and production tasks and activities in the western part of Java which includes onshore and offshore areas. Existing gas production in PEP Zone 7 continues to decline. The production performance...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/66719 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:66719 |
---|---|
spelling |
id-itb.:667192022-07-13T14:19:09ZDECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP Apriansyah, Bayu Manajemen umum Indonesia Theses Gas Field Development, Decision making, Analytical Hierarchy Process. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/66719 PT Pertamina EP (PEP) as a subsidiary of Upstream Holding Pertamina has a role to carry out exploration and production tasks and activities in the western part of Java which includes onshore and offshore areas. Existing gas production in PEP Zone 7 continues to decline. The production performance of the main structure that contributes to the achievement of gas production is not as good as 2000s. Referring to the company's commitment to SKK Migas through the WP&B event (Work Program and Budget) as well as the company's commitment to Holding through the RKAP (Company Work Plan and Budget) event, the achievement of gas production for PEP Zone 7 is only 94%. Referring to the gas balance it shows that the gas supply from PEP Zone 7 is not able to keep up with gas demand from consumers. PEP Zone 7 through the Subsurface Development Department conducted a study on potential structures to increase gas production and supply capability. One of them is Bumi Hitam Complex which consist of Bumi Hitam Structure and Cililin Selatan Structure. The latest subsurface study, the estimated recoverable reserve is about 24 BSCF and 150 MBO. This comes from one workover, two infill well drilling, and two step-outs drilling activities. The current issue is how to handle the produced fluid. The closest production facility to the BMH structure is the Gathering Station (GS) of North Cililin (CLU) which is 23 kilometers (km) away. Gas Compression Station (GCS) Cilamaya which is operated by PT. Pertagas is 17 km away. The closest distance to the network pipe is 10 km, but the pipe is at compressor discharge so it has high pressure. To resolve the problem, VFT (Value Focused Thinking) approach is used. It generates three scenarios: build new gathering station and transport the fluid to compressor suction, transport gross fluid to GS CLU, and build new gathering station and transport the fluid to compressor discharge. Those scenarios consider cost, hydrocarbon recovery, net present value, and operability. Analytical Hierarchy Process (AHP) is used to find the best solution. Four subject matter experts (SME) conduct FGD (Focused Group Discussion) to assess each scenario considering those criteria. It generates scenario to build new gathering station and transport the fluid to compressor suction as the best scenario with the value reach 59.3%. The consistency ratio is also valid with the value of 0.07 (valid value requirement is less than 0.1). text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Manajemen umum |
spellingShingle |
Manajemen umum Apriansyah, Bayu DECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP |
description |
PT Pertamina EP (PEP) as a subsidiary of Upstream Holding Pertamina has a role to carry out
exploration and production tasks and activities in the western part of Java which includes
onshore and offshore areas. Existing gas production in PEP Zone 7 continues to decline. The
production performance of the main structure that contributes to the achievement of gas
production is not as good as 2000s. Referring to the company's commitment to SKK Migas
through the WP&B event (Work Program and Budget) as well as the company's commitment
to Holding through the RKAP (Company Work Plan and Budget) event, the achievement of
gas production for PEP Zone 7 is only 94%. Referring to the gas balance it shows that the gas
supply from PEP Zone 7 is not able to keep up with gas demand from consumers. PEP Zone 7
through the Subsurface Development Department conducted a study on potential structures to
increase gas production and supply capability. One of them is Bumi Hitam Complex which
consist of Bumi Hitam Structure and Cililin Selatan Structure. The latest subsurface study, the
estimated recoverable reserve is about 24 BSCF and 150 MBO. This comes from one
workover, two infill well drilling, and two step-outs drilling activities. The current issue is how
to handle the produced fluid. The closest production facility to the BMH structure is the
Gathering Station (GS) of North Cililin (CLU) which is 23 kilometers (km) away. Gas
Compression Station (GCS) Cilamaya which is operated by PT. Pertagas is 17 km away. The
closest distance to the network pipe is 10 km, but the pipe is at compressor discharge so it has
high pressure. To resolve the problem, VFT (Value Focused Thinking) approach is used. It
generates three scenarios: build new gathering station and transport the fluid to compressor
suction, transport gross fluid to GS CLU, and build new gathering station and transport the
fluid to compressor discharge. Those scenarios consider cost, hydrocarbon recovery, net
present value, and operability. Analytical Hierarchy Process (AHP) is used to find the best
solution. Four subject matter experts (SME) conduct FGD (Focused Group Discussion) to
assess each scenario considering those criteria. It generates scenario to build new gathering
station and transport the fluid to compressor suction as the best scenario with the value reach
59.3%. The consistency ratio is also valid with the value of 0.07 (valid value requirement is
less than 0.1). |
format |
Theses |
author |
Apriansyah, Bayu |
author_facet |
Apriansyah, Bayu |
author_sort |
Apriansyah, Bayu |
title |
DECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP |
title_short |
DECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP |
title_full |
DECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP |
title_fullStr |
DECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP |
title_full_unstemmed |
DECISION ANALYSIS FOR BUMI HITAM FIELD DEVELOPMENT BY USING ANALYTICAL HIRARCHY PROCESS (AHP) CASE STUDY OF PT PERTAMINA EP |
title_sort |
decision analysis for bumi hitam field development by using analytical hirarchy process (ahp) case study of pt pertamina ep |
url |
https://digilib.itb.ac.id/gdl/view/66719 |
_version_ |
1822933133653180416 |