PT. Berau Coal as one of the largest coal producing companies in Indonesia will re-mine the previously finished pit at the Sambarata Mine Operation, namely Pit C2, where there is potential for coal reserves in the form of Premium Agathis Coal products. This premium product needs to be mixed with...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/71148 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:71148 |
---|---|
spelling |
id-itb.:711482023-01-27T14:02:38ZINVESTMENT PROJECT ANALYSIS OF MUD HANDLING USING SLURRY PUMP METHOD (CASE STUDY PIT C2 PT. BERAU COAL) Ihsan Priambodo, Mohamad Manajemen umum Indonesia Theses slurry pump, mud handling, cost efficiency, capital budgeting, probability analysis INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/71148 PT. Berau Coal as one of the largest coal producing companies in Indonesia will re-mine the previously finished pit at the Sambarata Mine Operation, namely Pit C2, where there is potential for coal reserves in the form of Premium Agathis Coal products. This premium product needs to be mixed with other products that have lower quality, specifically coal products from Binungan Mine Operation. In the current condition of Pit C2, the disposal for the allocation of overburden material disposal has a long distance and there is an additional cost incurred due to the distance rate adjustment from distance contract reference. To overcome this problem, there is an option of short distance disposal scenario, namely in pit dump scenario. With an in-pit dump scenario, there is cost efficiency from the distance rate adjustment due to the reduction in disposal distance. Sump H as a planned area for in pit dump is currently fulfilled with sedimentation material from previous mining activities, with a volume around 1,2 million cubic meters (BCM). Therefore, it is necessary for mud handling in Sump H area for it to become in pit dump location area. One of the proposed scenarios is the use of slurry pump, this scenario is more suitable for current condition due to it can finished earlier than other scenario, namely conventional mud handling. However, it is necessary to study and evaluate further the financial analysis of the proposed scenario in comprehensive manner. To obtain the financial feasibility of this project, this research use capital budgeting analysis in which the parameters used are studied further using sensitivity analysis and probability analysis. From the results of the financial feasibility analysis of this slurry pump scenario, it shows that this project is financially feasible with an NPV value of IDR 16.227.951.215,26, with an IRR of 43,08%, a Payback Period of 1,6 years, a Discounted Payback Period of 1,77 years and a Profitability value Index 1,7. In addition, based on the Monte Carlo Simulation for probability analysis, it is found that the probability of this project failing is 0%. Therefore, it can be concluded from the results of the financial feasibility analysis, this project is recommended to be implemented by PT. Berau Coal for cost efficiency incurred from distance rate adjustments. For future research, it can be research further for the option of purchase slurry pump rather than lease for bigger project. Other than that, to ensure the project running well, the research of best operational management method is needed for proper control of project running. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Manajemen umum |
spellingShingle |
Manajemen umum Ihsan Priambodo, Mohamad INVESTMENT PROJECT ANALYSIS OF MUD HANDLING USING SLURRY PUMP METHOD (CASE STUDY PIT C2 PT. BERAU COAL) |
description |
PT. Berau Coal as one of the largest coal producing companies in Indonesia will
re-mine the previously finished pit at the Sambarata Mine Operation, namely Pit
C2, where there is potential for coal reserves in the form of Premium Agathis
Coal products. This premium product needs to be mixed with other products that
have lower quality, specifically coal products from Binungan Mine Operation. In
the current condition of Pit C2, the disposal for the allocation of overburden
material disposal has a long distance and there is an additional cost incurred due
to the distance rate adjustment from distance contract reference. To overcome this
problem, there is an option of short distance disposal scenario, namely in pit dump
scenario. With an in-pit dump scenario, there is cost efficiency from the distance
rate adjustment due to the reduction in disposal distance. Sump H as a planned
area for in pit dump is currently fulfilled with sedimentation material from
previous mining activities, with a volume around 1,2 million cubic meters (BCM).
Therefore, it is necessary for mud handling in Sump H area for it to become in pit
dump location area. One of the proposed scenarios is the use of slurry pump, this
scenario is more suitable for current condition due to it can finished earlier than
other scenario, namely conventional mud handling. However, it is necessary to
study and evaluate further the financial analysis of the proposed scenario in
comprehensive manner. To obtain the financial feasibility of this project, this
research use capital budgeting analysis in which the parameters used are studied
further using sensitivity analysis and probability analysis.
From the results of the financial feasibility analysis of this slurry pump scenario, it
shows that this project is financially feasible with an NPV value of IDR
16.227.951.215,26, with an IRR of 43,08%, a Payback Period of 1,6 years, a
Discounted Payback Period of 1,77 years and a Profitability value Index 1,7. In
addition, based on the Monte Carlo Simulation for probability analysis, it is found
that the probability of this project failing is 0%. Therefore, it can be concluded
from the results of the financial feasibility analysis, this project is recommended
to be implemented by PT. Berau Coal for cost efficiency incurred from distance
rate adjustments. For future research, it can be research further for the option of
purchase slurry pump rather than lease for bigger project. Other than that, to
ensure the project running well, the research of best operational management
method is needed for proper control of project running. |
format |
Theses |
author |
Ihsan Priambodo, Mohamad |
author_facet |
Ihsan Priambodo, Mohamad |
author_sort |
Ihsan Priambodo, Mohamad |
title |
INVESTMENT PROJECT ANALYSIS OF MUD HANDLING USING SLURRY PUMP METHOD (CASE STUDY PIT C2 PT. BERAU COAL) |
title_short |
INVESTMENT PROJECT ANALYSIS OF MUD HANDLING USING SLURRY PUMP METHOD (CASE STUDY PIT C2 PT. BERAU COAL) |
title_full |
INVESTMENT PROJECT ANALYSIS OF MUD HANDLING USING SLURRY PUMP METHOD (CASE STUDY PIT C2 PT. BERAU COAL) |
title_fullStr |
INVESTMENT PROJECT ANALYSIS OF MUD HANDLING USING SLURRY PUMP METHOD (CASE STUDY PIT C2 PT. BERAU COAL) |
title_full_unstemmed |
INVESTMENT PROJECT ANALYSIS OF MUD HANDLING USING SLURRY PUMP METHOD (CASE STUDY PIT C2 PT. BERAU COAL) |
title_sort |
investment project analysis of mud handling using slurry pump method (case study pit c2 pt. berau coal) |
url |
https://digilib.itb.ac.id/gdl/view/71148 |
_version_ |
1822278974130094080 |