PENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING
PT Dirgantara Indonesia (PTDI) is one of the state-owned enterprises engaged in the manufacturing industry of aircraft. One of the areas in PTDI is the sheet metal area which has high workload. In 2022, there were 92 parts in this area that couldn't be completed on time. The sheet metal area...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/74497 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:74497 |
---|---|
spelling |
id-itb.:744972023-07-17T10:58:14ZPENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING Alexandra, Natasya Teknik (Rekayasa, enjinering dan kegiatan berkaitan) Indonesia Final Project scheduling, makespan, simulated annealing INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/74497 PT Dirgantara Indonesia (PTDI) is one of the state-owned enterprises engaged in the manufacturing industry of aircraft. One of the areas in PTDI is the sheet metal area which has high workload. In 2022, there were 92 parts in this area that couldn't be completed on time. The sheet metal area is divided into 5 cells, and one of them is cell 2, which has the largest contribution in the sheet metal area. About 70% of the parts that enter the sheet metal area are processed in cell 2. Therefore, minimizing the makespan in cell 2 can have a significant impact on reducing bottleneck and production delays. One way to minimize the makespan is by developing scheduling methods in cell 2. Simulated annealing algorithm (SA) is used to develop the scheduling method in cell 2. SA algorithm consists of two parts: the outer loop algorithm that used for running the general simulated annealing algorithm and the inner loop algorithm that used for generating new solutions and performing assignment procedures. The development of the simulated annealing algorithm is translated into a Python program to obtain the desired result, which is the production scheduling that minimizes the makespan. The algorithm is experimented using the full factorial design method to evaluate the makespan values. Based on the experimental results, significant factors are identified, including the final temperature (????????), cooling rate (????), and the number of iterations per temperature (????). Furthermore, recommendations were obtained for significant factor values that can be used to achieve minimum makespan, namely ???????? with a value of 1, ???? with a value of 0.95, and ???? with a value of 20. Based on the computational results using the recommended factors the makespan was improved by 24.61% compared to the priority scheduling method. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Teknik (Rekayasa, enjinering dan kegiatan berkaitan) |
spellingShingle |
Teknik (Rekayasa, enjinering dan kegiatan berkaitan) Alexandra, Natasya PENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING |
description |
PT Dirgantara Indonesia (PTDI) is one of the state-owned enterprises engaged
in the manufacturing industry of aircraft. One of the areas in PTDI is the sheet
metal area which has high workload. In 2022, there were 92 parts in this area
that couldn't be completed on time. The sheet metal area is divided into 5 cells,
and one of them is cell 2, which has the largest contribution in the sheet metal
area. About 70% of the parts that enter the sheet metal area are processed in
cell 2. Therefore, minimizing the makespan in cell 2 can have a significant
impact on reducing bottleneck and production delays. One way to minimize the
makespan is by developing scheduling methods in cell 2.
Simulated annealing algorithm (SA) is used to develop the scheduling method
in cell 2. SA algorithm consists of two parts: the outer loop algorithm that used
for running the general simulated annealing algorithm and the inner loop
algorithm that used for generating new solutions and performing assignment
procedures. The development of the simulated annealing algorithm is translated
into a Python program to obtain the desired result, which is the production
scheduling that minimizes the makespan.
The algorithm is experimented using the full factorial design method to evaluate
the makespan values. Based on the experimental results, significant factors are
identified, including the final temperature (????????), cooling rate (????), and the
number of iterations per temperature (????). Furthermore, recommendations
were obtained for significant factor values that can be used to achieve minimum
makespan, namely ???????? with a value of 1, ???? with a value of 0.95, and ???? with a
value of 20. Based on the computational results using the recommended factors
the makespan was improved by 24.61% compared to the priority scheduling
method. |
format |
Final Project |
author |
Alexandra, Natasya |
author_facet |
Alexandra, Natasya |
author_sort |
Alexandra, Natasya |
title |
PENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING |
title_short |
PENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING |
title_full |
PENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING |
title_fullStr |
PENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING |
title_full_unstemmed |
PENGEMBANGAN METODE PENJADWALAN PRODUKSI PADA AREA SHEET METAL DI PT DIRGANTARA INDONESIA DENGAN ALGORITMA SIMULATED ANNEALING |
title_sort |
pengembangan metode penjadwalan produksi pada area sheet metal di pt dirgantara indonesia dengan algoritma simulated annealing |
url |
https://digilib.itb.ac.id/gdl/view/74497 |
_version_ |
1822993826711601152 |