CORRELATION BETWEEN N-SPT, VP, VS AND ELASTIC MODULUS BASED ON GEOTECHNICAL AND GEOPHYSICAL SURVEY FOR YOGYAKARTA - BAWEN TUNNEL
Tunnels are a cheap means of transportation because they have a gentler slope, relatively cheaper development cost, and shorter mileage than surface transportation. Shear wave velocity (Vs), compressional wave velocity (Vp) and elastic modulus is an important parameter for tunnel design before tu...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/77161 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | Tunnels are a cheap means of transportation because they have a gentler slope,
relatively cheaper development cost, and shorter mileage than surface
transportation. Shear wave velocity (Vs), compressional wave velocity (Vp) and
elastic modulus is an important parameter for tunnel design before tunnel
construction is carried out. Unfortunately, determining in situ shear wave velocity
for large areas is expensive and takes along time. To overcome these problems, a
correlation between the standard penetration test (N-SPT), Vp, Vs and elastic
modulus. N-SPT data were obtained from a total of 41 boreholes ranging from 40
to 85 m in depth. Seismic downhole and seismic refraction were carried out to
obtain Vp and Vs data. Pressuremeter test was carried out to obtain elastic modulus
in-situ. The correlation between N-SPI ana Vp, Vs and elastic modulus in this study
has coefficient of determination (R2) value of 0.901, 0.878 and 0.693 respectively.
Comparison between measured and predicted data, normal consistency ratio and
scaled error percent graph were used to evaluate the performance of this study
correlation. Normal consistency ratio maximum of 12, 25 and 2 for Vp, Vs and
elastic modulus correlation respectively and more than 9096 Vp and Vs data has
less than 1099 error, but there is only 3529 elastic modulus data has less than 1020
error. Correlation between N-SPT and Vp and Vs can be used as a predictor to
estimate Vp and Vs value for initial design. |
---|