ANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY)

Embankment works on soft soil pose significant challenges in toll road construction. In the embankment work for the toll road project in Langkat Regency, locations with varying soft soil thicknesses were found, resulting in settlement in the roadbed. After conducting soil investigations, a thick lay...

Full description

Saved in:
Bibliographic Details
Main Author: Ikrimah
Format: Theses
Language:Indonesia
Subjects:
Online Access:https://digilib.itb.ac.id/gdl/view/87269
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:87269
spelling id-itb.:872692025-01-23T10:59:37ZANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY) Ikrimah Teknik sipil Indonesia Theses Soft Soil, Pile Embankment, Stone Column, Safety Factor, Settlement, Finite Element Method INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/87269 Embankment works on soft soil pose significant challenges in toll road construction. In the embankment work for the toll road project in Langkat Regency, locations with varying soft soil thicknesses were found, resulting in settlement in the roadbed. After conducting soil investigations, a thick layer of soft soil beneath the subgrade layer was discovered on the right side of the roadbed. This study aims to analyze the impact of soft soil on embankment stability and evaluate the soil reiriforcement methods applicable to the site. The study analyzes the initial design using three analysis models: Mohr-Coulomb, Hardening Soil, and Soft Soil models. Subsequently, reiriforcement methods were evaluated using two techniques: pile embankment and stone column, with the equations calibrated from the field soil investigation results to obtain accurate soil parameters. The analysis was performed using Finite Element Method (FEM) software, Plaxis 2D. The results showed that the failure conditions in the initial design were consistent with the findings from the additional soil investigation, where failure occurred at a 2-meter embankment depth. The pile embankment method yielded a minimum safety factor of 1.82 with a minimum settlement of-5.3 cm, while the stone column method resulted in a minimum safety factor of 1.29 with a minimum settlement of-8.5 cm. This study provides valuable insights into selecting the optimal soil reiriforcement method for embankment works on soft soil with varying layer thickness. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
topic Teknik sipil
spellingShingle Teknik sipil
Ikrimah
ANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY)
description Embankment works on soft soil pose significant challenges in toll road construction. In the embankment work for the toll road project in Langkat Regency, locations with varying soft soil thicknesses were found, resulting in settlement in the roadbed. After conducting soil investigations, a thick layer of soft soil beneath the subgrade layer was discovered on the right side of the roadbed. This study aims to analyze the impact of soft soil on embankment stability and evaluate the soil reiriforcement methods applicable to the site. The study analyzes the initial design using three analysis models: Mohr-Coulomb, Hardening Soil, and Soft Soil models. Subsequently, reiriforcement methods were evaluated using two techniques: pile embankment and stone column, with the equations calibrated from the field soil investigation results to obtain accurate soil parameters. The analysis was performed using Finite Element Method (FEM) software, Plaxis 2D. The results showed that the failure conditions in the initial design were consistent with the findings from the additional soil investigation, where failure occurred at a 2-meter embankment depth. The pile embankment method yielded a minimum safety factor of 1.82 with a minimum settlement of-5.3 cm, while the stone column method resulted in a minimum safety factor of 1.29 with a minimum settlement of-8.5 cm. This study provides valuable insights into selecting the optimal soil reiriforcement method for embankment works on soft soil with varying layer thickness.
format Theses
author Ikrimah
author_facet Ikrimah
author_sort Ikrimah
title ANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY)
title_short ANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY)
title_full ANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY)
title_fullStr ANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY)
title_full_unstemmed ANALYSIS OF EMBANKMENTS ON SOFT SOIL AREAS WITH LAYER THICKNESS VARIATIONS (CASE STUDY: TOLL ROAD IN LANGKAT REGENCY)
title_sort analysis of embankments on soft soil areas with layer thickness variations (case study: toll road in langkat regency)
url https://digilib.itb.ac.id/gdl/view/87269
_version_ 1822283655761887232