PEMAKAIAN DAYA LISTRIK AKTUAL DI PT. MITSUBISHI ELECTRIC AUTOMOTIVE INDONESIA
Actual Electrical Energy Consumption in PT. Mitsubishi Electric Automotive Indonesia. Energy using up / energy (Watt) electricity at corporate current very high, are not strictly for lighting requirement but also for production machine equipments.Usings up current count electricity aim to know requi...
Saved in:
Main Authors: | , |
---|---|
Format: | Theses and Dissertations NonPeerReviewed |
Published: |
[Yogyakarta] : Universitas Gadjah Mada
2014
|
Subjects: | |
Online Access: | https://repository.ugm.ac.id/127147/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=67391 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universitas Gadjah Mada |
Summary: | Actual Electrical Energy Consumption in PT. Mitsubishi Electric Automotive
Indonesia. Energy using up / energy (Watt) electricity at corporate current very
high, are not strictly for lighting requirement but also for production machine
equipments.Usings up current count electricity aim to know requirement &
electric energy purpose at PT. Mitsubishi Electric Automotive is Indonesia.Actual
calculation usings up current count electricity to know requirement & electric
energy purpose at PT. Mitsubishi Electric Automotive Indonesia.The research
conducted using electric current data methods and data load anotherelectricity to
calculate the electric energy used in PT. Mitsubishi Electric Automotive
Indonesia. PT. CikarangListrindo are electricity suplay for PT. Mitsubishi
Electric Automotive Indonesia as big as 1000 kVA and is divided on 3
transformer that gets capacity each 500 kVA.Energy using up point PT.
Mitsubishi Electric Automotive is Indonesia which is as big as 142,520 kWh /
moons until with 207,960 kWh / moon clings to long times and a lot of it type hads
out. |
---|