KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU RIAU
Palm Oil Factory PT. Inecda Plantation is a company engaged in oil palm processing argoindustri CPO (Crude Palm Oil. Palm oil processing, there are several stages of the process that requires energy needs. Required calculations in order to determine the maximum load for capacity and determine the ef...
Saved in:
Main Authors: | , |
---|---|
Format: | Theses and Dissertations NonPeerReviewed |
Published: |
[Yogyakarta] : Universitas Gadjah Mada
2014
|
Subjects: | |
Online Access: | https://repository.ugm.ac.id/127520/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=67779 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universitas Gadjah Mada |
id |
id-ugm-repo.127520 |
---|---|
record_format |
dspace |
spelling |
id-ugm-repo.1275202016-03-04T08:00:15Z https://repository.ugm.ac.id/127520/ KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU RIAU , MOHAMMAD JINDAR ALFARISI , Ir. Daroto, MT. ETD Palm Oil Factory PT. Inecda Plantation is a company engaged in oil palm processing argoindustri CPO (Crude Palm Oil. Palm oil processing, there are several stages of the process that requires energy needs. Required calculations in order to determine the maximum load for capacity and determine the efficiency of the power generated at the power plant ( Steam Power Plant) in the production process of palm oil processing PT. Inecda Plantation to the load capacity required in the production process. Observations on the activity of PT. Inecda Plantation has its own power generation system (power plant) with a capacity of 800 KW of electrical power, the output of steam after the turbine through the boiling process used for palm fruits using high-pressure steam. Research on electric power needs PT. The Plantation Inecda conducted from April 1 to April 30, 2013, with the sample for 30 days resulted in an average maximum power of 667.5 kW during the processing of palm oil production process takes place, where the size of a system tailored to the size of the plant production capacity the industry. [Yogyakarta] : Universitas Gadjah Mada 2014 Thesis NonPeerReviewed , MOHAMMAD JINDAR ALFARISI and , Ir. Daroto, MT. (2014) KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU RIAU. UNSPECIFIED thesis, UNSPECIFIED. http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=67779 |
institution |
Universitas Gadjah Mada |
building |
UGM Library |
country |
Indonesia |
collection |
Repository Civitas UGM |
topic |
ETD |
spellingShingle |
ETD , MOHAMMAD JINDAR ALFARISI , Ir. Daroto, MT. KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU RIAU |
description |
Palm Oil Factory PT. Inecda Plantation is a company engaged in oil palm processing
argoindustri CPO (Crude Palm Oil. Palm oil processing, there are several stages of the process
that requires energy needs. Required calculations in order to determine the maximum load for
capacity and determine the efficiency of the power generated at the power plant ( Steam Power
Plant) in the production process of palm oil processing PT. Inecda Plantation to the load
capacity required in the production process.
Observations on the activity of PT. Inecda Plantation has its own power generation
system (power plant) with a capacity of 800 KW of electrical power, the output of steam after the
turbine through the boiling process used for palm fruits using high-pressure steam. Research on
electric power needs PT. The Plantation Inecda conducted from April 1 to April 30, 2013, with
the sample for 30 days resulted in an average maximum power of 667.5 kW during the
processing of palm oil production process takes place, where the size of a system tailored to the
size of the plant production capacity the industry. |
format |
Theses and Dissertations NonPeerReviewed |
author |
, MOHAMMAD JINDAR ALFARISI , Ir. Daroto, MT. |
author_facet |
, MOHAMMAD JINDAR ALFARISI , Ir. Daroto, MT. |
author_sort |
, MOHAMMAD JINDAR ALFARISI |
title |
KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU
RIAU |
title_short |
KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU
RIAU |
title_full |
KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU
RIAU |
title_fullStr |
KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU
RIAU |
title_full_unstemmed |
KEBUTUHAN DAYA LISTRIK DI PABRIK KELAPA SAWIT PT INECDA PLANTATION SEBERIDA INDRAGIRI HULU
RIAU |
title_sort |
kebutuhan daya listrik di pabrik kelapa sawit pt inecda plantation seberida indragiri hulu
riau |
publisher |
[Yogyakarta] : Universitas Gadjah Mada |
publishDate |
2014 |
url |
https://repository.ugm.ac.id/127520/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=67779 |
_version_ |
1681232630667804672 |