Cost performance for building construction projects in Klang Valley
Since seventies, the economic of Malaysia has undergone rapid growth. Construction industry constitutes an important element of Malaysian economy. It shows how important to control and manage the projects in good quality and efficiently. There are four fundamental constraints needed to be conside...
Saved in:
Main Authors: | , |
---|---|
Format: | Article |
Language: | English |
Published: |
Penerbit UKM
2010
|
Online Access: | http://journalarticle.ukm.my/2525/1/paper07.pdf http://journalarticle.ukm.my/2525/ http://www.ukm.my/~jsb/jbp/index.html |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universiti Kebangsaan Malaysia |
Language: | English |
Summary: | Since seventies, the economic of Malaysia has undergone rapid growth. Construction
industry constitutes an important element of Malaysian economy. It shows how important
to control and manage the projects in good quality and efficiently. There are four
fundamental constraints needed to be considered when managing the construction
projects, which are scope, cost, time, and quality. In order to manage the projects
successfully, it is necessary to consider whether the project is within those four
constraints. However, it found that there were many problems on cost performance in
many countries. One of the major problems was cost overrun in construction projects. In
Malaysia, the problem of cost overrun considered significance in construction industry.
There were many factors that contribute to cost overrun in Malaysian construction
projects. The factors might become risks and lead to negative effect to the projects.
Hence, this research is to identify factors that contribute to cost overrun and potential
measures to overcome the problem with the focus given to construction projects within
Klang Valley. The method used in this research is quantitative based. A questionnaire
survey conducted to collect data from the respondents that consisted of project manager,
quantity surveyor, M & E Engineer, C & S Engineer, and other related respondents.
Questionnaires were distributed to 30 respondents from construction firms in Klang Valley.
Data collected form a database for analysis using Statistic Package for Social Sciences
(SPSS) version 17.0. Descriptive statistics and ranking analysis were used in data
analysis. The result shown that the most serious factor contributes to cost overrun was
inaccurate or poor estimation of original cost and the factor do not affect most was
mistake in design. The most important method to control construction cost is proper
project costing and financing. On the other hand, the least important approach was
establishing a system in design. In conclusion, the problem of cost overrun is not a small
issue but could cause serious problems to the construction industry in Malaysia. |
---|