Factors for containing failure and abandonment of public sector construction projects in Nigeria
The objective of this study was to identify possible factors that would minimize or contain failure and abandonment of public sector construction projects, evaluate the identified factors in their order of importance. Data on the study variables were collected through structured questionnaire from...
Saved in:
Main Authors: | , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
Penerbit UKM
2015
|
Online Access: | http://journalarticle.ukm.my/9123/1/143-491-1-PB.pdf http://journalarticle.ukm.my/9123/ http://spaj.ukm.my/jsb/index.php/jbp/issue/view/29 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universiti Kebangsaan Malaysia |
Language: | English |
Summary: | The objective of this study was to identify possible factors that would minimize or contain failure and
abandonment of public sector construction projects, evaluate the identified factors in their order of
importance. Data on the study variables were collected through structured questionnaire from
construction firms located in Imo, Abia and Rivers States of Nigeria with wealth of experience in failed
and abandoned public sector construction projects. Respondents were approached personally to
collect the data. A total of three hundred (300) questionnaires were distributed while two hundred and
fifty three (253) were retrieved and used for analysis. Various statistical tools such as descriptive
statistics, cronbach's alpha test, as well as relative importance index with the aid of SPSS and
Microsoft Excel were applied for data analysis and inference. The results of the study revealed that
nine factors were critical in containing failure and abandonment of public sector construction projects
in Nigeria. The factors include; Detailed and Comprehensive Design by the Contractors, Effective
Monitoring, Understanding of Project’s Mission, Technical Knowhow of the Project Manager, Support
from Top Management, Political Risks, Effective Procurement Process, Provision of Adequate
Finance by the Client, and Effective Communication and Information Management by Design Team. |
---|