Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati

There is always a potential hazard that can cause losses to project constructions. Risk management is a way to accommodate risks that may occur during the construction period. The purpose of this study is to identify the dominant risk in construction activities and to recommend risk control measures...

Full description

Saved in:
Bibliographic Details
Main Authors: Sapitri, Sritika Arfilia, Harmiyati
Format: Article
Language:English
Published: Penerbit PRESS, Universiti Teknologi MARA 2024
Subjects:
Online Access:https://ir.uitm.edu.my/id/eprint/95411/1/95411.pdf
https://ir.uitm.edu.my/id/eprint/95411/
https://jsst.uitm.edu.my/index.php/jsst/index
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Universiti Teknologi Mara
Language: English
id my.uitm.ir.95411
record_format eprints
spelling my.uitm.ir.954112024-05-17T02:26:49Z https://ir.uitm.edu.my/id/eprint/95411/ Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati jsst Sapitri Sritika Arfilia Harmiyati Industrial engineering. Management engineering Dams. Barrages There is always a potential hazard that can cause losses to project constructions. Risk management is a way to accommodate risks that may occur during the construction period. The purpose of this study is to identify the dominant risk in construction activities and to recommend risk control measures. This study uses the Failure Mode and Effect Analysis method. The focus of risk identification was carried out during the construction phase and involved a total of 56 respondents. The research results showed that there were eight risk variables identified as dominant risks. The dominant risks were: (i) shortage of material landfills, (ii) labour negligence, (iii) lack of awareness of workers using PPE, (iv) heavy equipment accident, (v) unstable soil condition, (vi) groundwater level condition, (vii) unclean project environment, and (viii) noisy project environment. The risk that occurs in implementing construction projects have an impact on the project’s productivity, directly or indirectly. Although there are different risks, some risks are recommended with the same handling method, especially consistency in doing work with SOPs, monitoring employee discipline and using appropriate work methods. Penerbit PRESS, Universiti Teknologi MARA 2024-03 Article PeerReviewed text en https://ir.uitm.edu.my/id/eprint/95411/1/95411.pdf Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati. (2024) Journal of Smart Science and Technology <https://ir.uitm.edu.my/view/publication/Journal_of_Smart_Science_and_Technology/>, 4 (1): 5. pp. 57-66. ISSN 2785-924X https://jsst.uitm.edu.my/index.php/jsst/index
institution Universiti Teknologi Mara
building Tun Abdul Razak Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Teknologi Mara
content_source UiTM Institutional Repository
url_provider http://ir.uitm.edu.my/
language English
topic Industrial engineering. Management engineering
Dams. Barrages
spellingShingle Industrial engineering. Management engineering
Dams. Barrages
Sapitri
Sritika Arfilia
Harmiyati
Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati
description There is always a potential hazard that can cause losses to project constructions. Risk management is a way to accommodate risks that may occur during the construction period. The purpose of this study is to identify the dominant risk in construction activities and to recommend risk control measures. This study uses the Failure Mode and Effect Analysis method. The focus of risk identification was carried out during the construction phase and involved a total of 56 respondents. The research results showed that there were eight risk variables identified as dominant risks. The dominant risks were: (i) shortage of material landfills, (ii) labour negligence, (iii) lack of awareness of workers using PPE, (iv) heavy equipment accident, (v) unstable soil condition, (vi) groundwater level condition, (vii) unclean project environment, and (viii) noisy project environment. The risk that occurs in implementing construction projects have an impact on the project’s productivity, directly or indirectly. Although there are different risks, some risks are recommended with the same handling method, especially consistency in doing work with SOPs, monitoring employee discipline and using appropriate work methods.
format Article
author Sapitri
Sritika Arfilia
Harmiyati
author_facet Sapitri
Sritika Arfilia
Harmiyati
author_sort Sapitri
title Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati
title_short Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati
title_full Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati
title_fullStr Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati
title_full_unstemmed Risk analysis of small dam projects in Lima Puluh Kota area using Failure Mode and Effect Analysis / Sapitri, Sritika Afrilia and Harmiyati
title_sort risk analysis of small dam projects in lima puluh kota area using failure mode and effect analysis / sapitri, sritika afrilia and harmiyati
publisher Penerbit PRESS, Universiti Teknologi MARA
publishDate 2024
url https://ir.uitm.edu.my/id/eprint/95411/1/95411.pdf
https://ir.uitm.edu.my/id/eprint/95411/
https://jsst.uitm.edu.my/index.php/jsst/index
_version_ 1800100663973117952