Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan

Delivering successful rail projects has always been extremely difficult. The fact is widely discussed in developed nations as their outstanding rail networks were known to have significant cost overruns. A comprehensive rail network is progressing in developing nations, and cost overruns have alread...

Full description

Saved in:
Bibliographic Details
Main Authors: Ismail, Mohamad Zahierruden, Mohamad Ramly, Zuhaili, Misnan, Mohd Saidin
Format: Article
Language:English
Published: Universiti Teknologi MARA, Perak 2024
Subjects:
Online Access:https://ir.uitm.edu.my/id/eprint/98941/1/98941.pdf
https://ir.uitm.edu.my/id/eprint/98941/
https://journal.uitm.edu.my/ojs/index.php/MySE/issue/view/62
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Universiti Teknologi Mara
Language: English
id my.uitm.ir.98941
record_format eprints
spelling my.uitm.ir.989412024-09-18T18:31:22Z https://ir.uitm.edu.my/id/eprint/98941/ Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan myse Ismail, Mohamad Zahierruden Mohamad Ramly, Zuhaili Misnan, Mohd Saidin NA Architecture Transportation buildings Delivering successful rail projects has always been extremely difficult. The fact is widely discussed in developed nations as their outstanding rail networks were known to have significant cost overruns. A comprehensive rail network is progressing in developing nations, and cost overruns have already occurred in nations like China and India. The problem is critical in Malaysia, where poor cost performance has been highlighted for decades. This study aims to establish the significant influences on cost performance of rail projects, by assessing the critical influences that may affect project cost management. Primary data was gathered from 100 cost managers in the rail construction industry. Five (5) main component elements were discovered with a total of fifty (50) related items based on prior studies. Project estimation, project planning, project management, technical experience, and project complexity can be categorized as the primary component aspects. The influences and their respective items are then utilized to create the questionnaire for gathering data. Collected data were then analyzed using Exploratory Factor Analysis (EFA), which focused on the five (5) components and fifty (50) influences that affected rail construction cost performance. The overall variance percentage was 62.514%. Each component has a minimum of four variables, thus complying with the requisite that every component needs a minimum of three variables. Universiti Teknologi MARA, Perak 2024-03 Article PeerReviewed text en https://ir.uitm.edu.my/id/eprint/98941/1/98941.pdf Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan. (2024) Malaysian Journal of Sustainable Environment (MySE) <https://ir.uitm.edu.my/view/publication/Malaysian_Journal_of_Sustainable_Environment_=28MySE=29/>, 11 (1). pp. 147-176. ISSN 0128-326X https://journal.uitm.edu.my/ojs/index.php/MySE/issue/view/62 10.24191/myse.v11i1.993 10.24191/myse.v11i1.993 10.24191/myse.v11i1.993
institution Universiti Teknologi Mara
building Tun Abdul Razak Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Teknologi Mara
content_source UiTM Institutional Repository
url_provider http://ir.uitm.edu.my/
language English
topic NA Architecture
Transportation buildings
spellingShingle NA Architecture
Transportation buildings
Ismail, Mohamad Zahierruden
Mohamad Ramly, Zuhaili
Misnan, Mohd Saidin
Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan
description Delivering successful rail projects has always been extremely difficult. The fact is widely discussed in developed nations as their outstanding rail networks were known to have significant cost overruns. A comprehensive rail network is progressing in developing nations, and cost overruns have already occurred in nations like China and India. The problem is critical in Malaysia, where poor cost performance has been highlighted for decades. This study aims to establish the significant influences on cost performance of rail projects, by assessing the critical influences that may affect project cost management. Primary data was gathered from 100 cost managers in the rail construction industry. Five (5) main component elements were discovered with a total of fifty (50) related items based on prior studies. Project estimation, project planning, project management, technical experience, and project complexity can be categorized as the primary component aspects. The influences and their respective items are then utilized to create the questionnaire for gathering data. Collected data were then analyzed using Exploratory Factor Analysis (EFA), which focused on the five (5) components and fifty (50) influences that affected rail construction cost performance. The overall variance percentage was 62.514%. Each component has a minimum of four variables, thus complying with the requisite that every component needs a minimum of three variables.
format Article
author Ismail, Mohamad Zahierruden
Mohamad Ramly, Zuhaili
Misnan, Mohd Saidin
author_facet Ismail, Mohamad Zahierruden
Mohamad Ramly, Zuhaili
Misnan, Mohd Saidin
author_sort Ismail, Mohamad Zahierruden
title Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan
title_short Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan
title_full Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan
title_fullStr Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan
title_full_unstemmed Analysing the significant influences of cost performance in Malaysian rail projects: exploratory factor analysis / Mohamad Zahierruden Ismail, Zuhaili Mohamad Ramly and Mohd Saidin Misnan
title_sort analysing the significant influences of cost performance in malaysian rail projects: exploratory factor analysis / mohamad zahierruden ismail, zuhaili mohamad ramly and mohd saidin misnan
publisher Universiti Teknologi MARA, Perak
publishDate 2024
url https://ir.uitm.edu.my/id/eprint/98941/1/98941.pdf
https://ir.uitm.edu.my/id/eprint/98941/
https://journal.uitm.edu.my/ojs/index.php/MySE/issue/view/62
_version_ 1811598105828655104