Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop

Payment like interim payment is the most important in construction projects because it is the lifeblood that keeps the project operating efficiently. Timely and accurate payments are necessary to maintain a good cash flow, allowing contractors to meet their financial obligations to pay workers. Howe...

Full description

Saved in:
Bibliographic Details
Main Authors: Abdul Halim, Nurul Izzati, Lop, Nor Suzila
Format: Conference or Workshop Item
Language:English
Published: 2023
Subjects:
Online Access:https://ir.uitm.edu.my/id/eprint/99695/1/99695.pdf
https://ir.uitm.edu.my/id/eprint/99695/
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Universiti Teknologi Mara
Language: English
id my.uitm.ir.99695
record_format eprints
spelling my.uitm.ir.996952024-09-25T16:08:34Z https://ir.uitm.edu.my/id/eprint/99695/ Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop Abdul Halim, Nurul Izzati Lop, Nor Suzila Estimates. Measurements. Quantities and cost Payment like interim payment is the most important in construction projects because it is the lifeblood that keeps the project operating efficiently. Timely and accurate payments are necessary to maintain a good cash flow, allowing contractors to meet their financial obligations to pay workers. However, the construction project is prone to numerous payment problems, such as delayed payment and non-payment. Delayed payment is a common issue in which contractors are not paid on time, resulting in cash flow problems and significant project delays. The objective of this research was to identify the factors contributing to progress payment problems in Malaysian construction projects. The research methodology used was a quantitative method via a questionnaire survey. A total of 106 questionnaires has been distributed to grade G1 until G5 contractor in Klang Valley through a stratified random sampling method, and 52 questionnaires have been returned. The Statistical Package for the Social Sciences (SPSS) version 28 software was used to analyse the data. From the findings, it was found that most of the respondents agreed with the factors contributing to progress payment problems in Malaysian construction projects. The findings will help the project stakeholders overcome the payment problems and ensure project completion within the specified time, cost, and quality. 2023-10 Conference or Workshop Item PeerReviewed text en https://ir.uitm.edu.my/id/eprint/99695/1/99695.pdf Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop. (2023) In: UNSPECIFIED.
institution Universiti Teknologi Mara
building Tun Abdul Razak Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Teknologi Mara
content_source UiTM Institutional Repository
url_provider http://ir.uitm.edu.my/
language English
topic Estimates. Measurements. Quantities and cost
spellingShingle Estimates. Measurements. Quantities and cost
Abdul Halim, Nurul Izzati
Lop, Nor Suzila
Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop
description Payment like interim payment is the most important in construction projects because it is the lifeblood that keeps the project operating efficiently. Timely and accurate payments are necessary to maintain a good cash flow, allowing contractors to meet their financial obligations to pay workers. However, the construction project is prone to numerous payment problems, such as delayed payment and non-payment. Delayed payment is a common issue in which contractors are not paid on time, resulting in cash flow problems and significant project delays. The objective of this research was to identify the factors contributing to progress payment problems in Malaysian construction projects. The research methodology used was a quantitative method via a questionnaire survey. A total of 106 questionnaires has been distributed to grade G1 until G5 contractor in Klang Valley through a stratified random sampling method, and 52 questionnaires have been returned. The Statistical Package for the Social Sciences (SPSS) version 28 software was used to analyse the data. From the findings, it was found that most of the respondents agreed with the factors contributing to progress payment problems in Malaysian construction projects. The findings will help the project stakeholders overcome the payment problems and ensure project completion within the specified time, cost, and quality.
format Conference or Workshop Item
author Abdul Halim, Nurul Izzati
Lop, Nor Suzila
author_facet Abdul Halim, Nurul Izzati
Lop, Nor Suzila
author_sort Abdul Halim, Nurul Izzati
title Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop
title_short Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop
title_full Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop
title_fullStr Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop
title_full_unstemmed Factors contributing to progress payment problems in Malaysian construction projects / Nurul Izzati Abdul Halim and Nor Suzila Lop
title_sort factors contributing to progress payment problems in malaysian construction projects / nurul izzati abdul halim and nor suzila lop
publishDate 2023
url https://ir.uitm.edu.my/id/eprint/99695/1/99695.pdf
https://ir.uitm.edu.my/id/eprint/99695/
_version_ 1811598123092410368