An end-use energy analysis in a Malaysian public hospital

The commercial sector consumes 8-50 of the total energy consumption for a few selected countries around the world. An energy audit was conducted in a Malaysian public hospital to identify energy using equipment and their energy consumption breakdown. Different energy saving measures have been identi...

Full description

Saved in:
Bibliographic Details
Main Authors: Saidur, Rahman, Hasanuzzaman, M., Yogeswaran, S., Mohammed, H.A., Hossain, M.S.
Format: Article
Published: Energy 2010
Subjects:
Online Access:http://eprints.um.edu.my/6733/
http://ac.els-cdn.com/S0360544210004913/1-s2.0-S0360544210004913-main.pdf?_tid=26125430-4024-11e2-b37d-00000aacb35f&acdnat=1354853657_11da76e8151e0a79cd1969a6707e8fb8
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Universiti Malaya
id my.um.eprints.6733
record_format eprints
spelling my.um.eprints.67332019-10-25T06:08:59Z http://eprints.um.edu.my/6733/ An end-use energy analysis in a Malaysian public hospital Saidur, Rahman Hasanuzzaman, M. Yogeswaran, S. Mohammed, H.A. Hossain, M.S. TA Engineering (General). Civil engineering (General) TJ Mechanical engineering and machinery The commercial sector consumes 8-50 of the total energy consumption for a few selected countries around the world. An energy audit was conducted in a Malaysian public hospital to identify energy using equipment and their energy consumption breakdown. Different energy saving measures have been identified and applied for electrical motors used in this hospital. It was estimated that this hospital consumed about 19,311 MW h for the year 2008. It was also estimated that about 212 MW h, 250 MW h and 317 MW h of annual energy can be saved using energy-efficient motors at 50, 75 and 100 loads, respectively. In addition, use of variable speed drives are expected to save 1735 MW h, 4048 MW h and 6361 MW h of annual energy consumption for 20, 40 and 60 speed reductions, respectively. It was found that the payback period for using high efficiency motors at different loads is less than a year which is economically very viable. However, the use of variable speed drives was found to be economically viable for larger motors for higher speed reductions. The study also found that a sizeable amount of emissions can be reduced for the different energy savings measures applied for electrical motors. Energy 2010 Article PeerReviewed Saidur, Rahman and Hasanuzzaman, M. and Yogeswaran, S. and Mohammed, H.A. and Hossain, M.S. (2010) An end-use energy analysis in a Malaysian public hospital. Energy, 35 (12). pp. 4780-4785. ISSN 0360-5442 http://ac.els-cdn.com/S0360544210004913/1-s2.0-S0360544210004913-main.pdf?_tid=26125430-4024-11e2-b37d-00000aacb35f&acdnat=1354853657_11da76e8151e0a79cd1969a6707e8fb8 10.1016/j.energy.2010.09.012
institution Universiti Malaya
building UM Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Malaya
content_source UM Research Repository
url_provider http://eprints.um.edu.my/
topic TA Engineering (General). Civil engineering (General)
TJ Mechanical engineering and machinery
spellingShingle TA Engineering (General). Civil engineering (General)
TJ Mechanical engineering and machinery
Saidur, Rahman
Hasanuzzaman, M.
Yogeswaran, S.
Mohammed, H.A.
Hossain, M.S.
An end-use energy analysis in a Malaysian public hospital
description The commercial sector consumes 8-50 of the total energy consumption for a few selected countries around the world. An energy audit was conducted in a Malaysian public hospital to identify energy using equipment and their energy consumption breakdown. Different energy saving measures have been identified and applied for electrical motors used in this hospital. It was estimated that this hospital consumed about 19,311 MW h for the year 2008. It was also estimated that about 212 MW h, 250 MW h and 317 MW h of annual energy can be saved using energy-efficient motors at 50, 75 and 100 loads, respectively. In addition, use of variable speed drives are expected to save 1735 MW h, 4048 MW h and 6361 MW h of annual energy consumption for 20, 40 and 60 speed reductions, respectively. It was found that the payback period for using high efficiency motors at different loads is less than a year which is economically very viable. However, the use of variable speed drives was found to be economically viable for larger motors for higher speed reductions. The study also found that a sizeable amount of emissions can be reduced for the different energy savings measures applied for electrical motors.
format Article
author Saidur, Rahman
Hasanuzzaman, M.
Yogeswaran, S.
Mohammed, H.A.
Hossain, M.S.
author_facet Saidur, Rahman
Hasanuzzaman, M.
Yogeswaran, S.
Mohammed, H.A.
Hossain, M.S.
author_sort Saidur, Rahman
title An end-use energy analysis in a Malaysian public hospital
title_short An end-use energy analysis in a Malaysian public hospital
title_full An end-use energy analysis in a Malaysian public hospital
title_fullStr An end-use energy analysis in a Malaysian public hospital
title_full_unstemmed An end-use energy analysis in a Malaysian public hospital
title_sort end-use energy analysis in a malaysian public hospital
publisher Energy
publishDate 2010
url http://eprints.um.edu.my/6733/
http://ac.els-cdn.com/S0360544210004913/1-s2.0-S0360544210004913-main.pdf?_tid=26125430-4024-11e2-b37d-00000aacb35f&acdnat=1354853657_11da76e8151e0a79cd1969a6707e8fb8
_version_ 1648736065052213248