The adoption of industrialized building system (IBS) needs different method to cope with its dissimilar with traditional construction as it requires different process on design, installation and precision, but yet IBS always been treated the same as conventional projects. This cause problems and...
Saved in:
Main Authors: | , |
---|---|
Format: | Proceeding |
Language: | English |
Published: |
2021
|
Subjects: | |
Online Access: | http://ir.unimas.my/id/eprint/37202/1/Shazwan%20Mohamed%20Shaari.pdf http://ir.unimas.my/id/eprint/37202/ https://icrmbee.uitm.edu.my/ |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universiti Malaysia Sarawak |
Language: | English |
id |
my.unimas.ir.37202 |
---|---|
record_format |
eprints |
spelling |
my.unimas.ir.372022021-12-16T06:29:33Z http://ir.unimas.my/id/eprint/37202/ Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects Ahmad, Abd Jalil Shazwan, Mohamed Shaari TH Building construction The adoption of industrialized building system (IBS) needs different method to cope with its dissimilar with traditional construction as it requires different process on design, installation and precision, but yet IBS always been treated the same as conventional projects. This cause problems and thus, this study provide a questionnaire survey comprising 24 questions delivered to experienced professionals who involved in Malaysian IBS housing projects. The aim is to ascertain the challenges and suggest solutions on procuring the IBS components focusing for Malaysian IBS housing. The collected result was then verified through several semistructured interviews with experienced professionals from various field involve in IBS. This study finds that the main challenges in procuring IBS components are surround by factors on price, logistical barriers, and inadequacy on terms of agreement, The result also revealed in most IBS housing projects, the contract agreement between IBS manufacturers and main contractors were often breached especially on payment mechanism, amount and delivery time. Due to payment problems, some IBS manufacturers take unilateral action by stop delivery the IBS components, causing delay to the project, while others pursue the case to court, which also prolong into litigation. Contribution of this research is on the highlighting several urgent issues in the context of procuring IBS components for Malaysian housing. The findings reveal due to the unsolved issues, IBS targets to reduce cost and faster completion is hard to achieve, while exposing the project to end with delay or litigation. 2021 Proceeding PeerReviewed text en http://ir.unimas.my/id/eprint/37202/1/Shazwan%20Mohamed%20Shaari.pdf Ahmad, Abd Jalil and Shazwan, Mohamed Shaari (2021) Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects. In: 5TH International Conference on Research Methodology For Built Environment and Engineering (ICRMBEE 2021), 10 November 2021, UiTM Shah Alam. (In Press) https://icrmbee.uitm.edu.my/ |
institution |
Universiti Malaysia Sarawak |
building |
Centre for Academic Information Services (CAIS) |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Malaysia Sarawak |
content_source |
UNIMAS Institutional Repository |
url_provider |
http://ir.unimas.my/ |
language |
English |
topic |
TH Building construction |
spellingShingle |
TH Building construction Ahmad, Abd Jalil Shazwan, Mohamed Shaari Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects |
description |
The adoption of industrialized building system (IBS) needs different method to cope
with its dissimilar with traditional construction as it requires different process on design,
installation and precision, but yet IBS always been treated the same as conventional projects.
This cause problems and thus, this study provide a questionnaire survey comprising 24 questions
delivered to experienced professionals who involved in Malaysian IBS housing projects. The
aim is to ascertain the challenges and suggest solutions on procuring the IBS components
focusing for Malaysian IBS housing. The collected result was then verified through several semistructured interviews with experienced professionals from various field involve in IBS. This
study finds that the main challenges in procuring IBS components are surround by factors on
price, logistical barriers, and inadequacy on terms of agreement, The result also revealed in most
IBS housing projects, the contract agreement between IBS manufacturers and main contractors
were often breached especially on payment mechanism, amount and delivery time. Due to
payment problems, some IBS manufacturers take unilateral action by stop delivery the IBS
components, causing delay to the project, while others pursue the case to court, which also
prolong into litigation. Contribution of this research is on the highlighting several urgent issues
in the context of procuring IBS components for Malaysian housing. The findings reveal due to
the unsolved issues, IBS targets to reduce cost and faster completion is hard to achieve, while
exposing the project to end with delay or litigation. |
format |
Proceeding |
author |
Ahmad, Abd Jalil Shazwan, Mohamed Shaari |
author_facet |
Ahmad, Abd Jalil Shazwan, Mohamed Shaari |
author_sort |
Ahmad, Abd Jalil |
title |
Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects |
title_short |
Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects |
title_full |
Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects |
title_fullStr |
Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects |
title_full_unstemmed |
Exploring the Hurdles and Solutions in Procuring IBS Components for Malaysian Housing Projects |
title_sort |
exploring the hurdles and solutions in procuring ibs components for malaysian housing projects |
publishDate |
2021 |
url |
http://ir.unimas.my/id/eprint/37202/1/Shazwan%20Mohamed%20Shaari.pdf http://ir.unimas.my/id/eprint/37202/ https://icrmbee.uitm.edu.my/ |
_version_ |
1720440430788608000 |