Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit

. The goal of the retrofit at Zamrud substation is to transform a 28 MVA power transformer's neutral point grounding system from direct grounding to grounding using a 20 Ohm Neutral Grounding Resistor (NGR). The amount of short-circuit current produced will fluctuate with the installation of NG...

Full description

Saved in:
Bibliographic Details
Main Authors: Hamzah, Eteruddin, Arlenny, -, Hadiana, Siswanto, Yanuar Z., Arief, Fathimah, Hasanti
Format: Proceeding
Language:English
Published: IOP Publishing 2022
Online Access:http://ir.unimas.my/id/eprint/40381/1/Resetting%20the%20ground%20-%20Copy.pdf
http://ir.unimas.my/id/eprint/40381/
https://iopscience.iop.org/article/10.1088/1755-1315/1041/1/012021
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Universiti Malaysia Sarawak
Language: English
id my.unimas.ir.40381
record_format eprints
spelling my.unimas.ir.403812022-11-09T02:43:11Z http://ir.unimas.my/id/eprint/40381/ Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit Hamzah, Eteruddin Arlenny, - Hadiana, Siswanto Yanuar Z., Arief Fathimah, Hasanti . The goal of the retrofit at Zamrud substation is to transform a 28 MVA power transformer's neutral point grounding system from direct grounding to grounding using a 20 Ohm Neutral Grounding Resistor (NGR). The amount of short-circuit current produced will fluctuate with the installation of NGR. It is necessary to re-setting the Ground Fault Relay (GFR) on Zamrud substation. To estimate the value of the short-circuit current after installing the NGR, the impedance matrix approach is used to calculate it. According to the results, LG's largest short-circuit current is 397.83 A and its smallest is 313.55 A. Meanwhile LLG has a maximum short-circuit current of 5.334.30 A and a minimum short-circuit current of 943.31 A. Therefore, after NGR installation, the value of the relay setting is as follows: GFR pickup current on the transformer grounding GFR relay is 234.29 A, GFR pickup current on the neutral feeder 1 is 19.96 A, GFR pickup current on the neutral feeder 2 is 30.42 A, and GFR pickup current on the neutral feeder 3 is 38.40 A. IOP Publishing 2022 Proceeding PeerReviewed text en http://ir.unimas.my/id/eprint/40381/1/Resetting%20the%20ground%20-%20Copy.pdf Hamzah, Eteruddin and Arlenny, - and Hadiana, Siswanto and Yanuar Z., Arief and Fathimah, Hasanti (2022) Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit. In: 2021 International Conference on Environmental, Energy and Earth Science, ICEEES 2021, 22-23 September 2021, Virtual, Online. https://iopscience.iop.org/article/10.1088/1755-1315/1041/1/012021 doi:10.1088/1755-1315/1041/1/012021
institution Universiti Malaysia Sarawak
building Centre for Academic Information Services (CAIS)
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Malaysia Sarawak
content_source UNIMAS Institutional Repository
url_provider http://ir.unimas.my/
language English
description . The goal of the retrofit at Zamrud substation is to transform a 28 MVA power transformer's neutral point grounding system from direct grounding to grounding using a 20 Ohm Neutral Grounding Resistor (NGR). The amount of short-circuit current produced will fluctuate with the installation of NGR. It is necessary to re-setting the Ground Fault Relay (GFR) on Zamrud substation. To estimate the value of the short-circuit current after installing the NGR, the impedance matrix approach is used to calculate it. According to the results, LG's largest short-circuit current is 397.83 A and its smallest is 313.55 A. Meanwhile LLG has a maximum short-circuit current of 5.334.30 A and a minimum short-circuit current of 943.31 A. Therefore, after NGR installation, the value of the relay setting is as follows: GFR pickup current on the transformer grounding GFR relay is 234.29 A, GFR pickup current on the neutral feeder 1 is 19.96 A, GFR pickup current on the neutral feeder 2 is 30.42 A, and GFR pickup current on the neutral feeder 3 is 38.40 A.
format Proceeding
author Hamzah, Eteruddin
Arlenny, -
Hadiana, Siswanto
Yanuar Z., Arief
Fathimah, Hasanti
spellingShingle Hamzah, Eteruddin
Arlenny, -
Hadiana, Siswanto
Yanuar Z., Arief
Fathimah, Hasanti
Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit
author_facet Hamzah, Eteruddin
Arlenny, -
Hadiana, Siswanto
Yanuar Z., Arief
Fathimah, Hasanti
author_sort Hamzah, Eteruddin
title Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit
title_short Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit
title_full Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit
title_fullStr Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit
title_full_unstemmed Resetting the ground fault relay on a 28 MVA power transformer due to grounding method retrofit
title_sort resetting the ground fault relay on a 28 mva power transformer due to grounding method retrofit
publisher IOP Publishing
publishDate 2022
url http://ir.unimas.my/id/eprint/40381/1/Resetting%20the%20ground%20-%20Copy.pdf
http://ir.unimas.my/id/eprint/40381/
https://iopscience.iop.org/article/10.1088/1755-1315/1041/1/012021
_version_ 1751540609563230208