Time Delay and Cost Overrun of Road over Bridge (ROB) Construction Projects in India
This paper aims at studying the factors that contribute to time delay and cost overrun of Road over Bridge (ROB) projects in India. Data for the research study were collected from 62 respondents, including owners, contractors, and consultants of ROB projects. The literature survey and the questio...
Saved in:
Main Authors: | , |
---|---|
Format: | Article |
Language: | English |
Published: |
Penerbit Universiti Sains Malaysia
2017
|
Subjects: | |
Online Access: | http://eprints.usm.my/41426/1/jcdc2017.22.s1.5.pdf http://eprints.usm.my/41426/ http://web.usm.my/jcdc/vol22_s1_2017/jcdc2017.22.s1.5.pdf |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Universiti Sains Malaysia |
Language: | English |
id |
my.usm.eprints.41426 |
---|---|
record_format |
eprints |
spelling |
my.usm.eprints.41426 http://eprints.usm.my/41426/ Time Delay and Cost Overrun of Road over Bridge (ROB) Construction Projects in India Venkateswaran, Chandrasekaran Balaji Murugasan, Rajiah TH1-9745 Building construction This paper aims at studying the factors that contribute to time delay and cost overrun of Road over Bridge (ROB) projects in India. Data for the research study were collected from 62 respondents, including owners, contractors, and consultants of ROB projects. The literature survey and the questionnaire survey helped in identifying 29 factors. The topmost factors were ranked based on the frequency of occurrences. The correlation among owners, contractors, and consultants on ranking of factors was derived by Spearman rank correlation. Factor analysis was used to classify the factors into groups and identify the key groups responsible for time delay and cost overrun of projects. This study will help all stakeholders of ROB projects in India to understand the factors and thereby reduce time delay and cost overrun as well as expedite their completion. Penerbit Universiti Sains Malaysia 2017 Article PeerReviewed application/pdf en http://eprints.usm.my/41426/1/jcdc2017.22.s1.5.pdf Venkateswaran, Chandrasekaran Balaji and Murugasan, Rajiah (2017) Time Delay and Cost Overrun of Road over Bridge (ROB) Construction Projects in India. Journal of Construction in Developing Countries , 22 (1). pp. 79-96. ISSN 1823-6499 http://web.usm.my/jcdc/vol22_s1_2017/jcdc2017.22.s1.5.pdf |
institution |
Universiti Sains Malaysia |
building |
Hamzah Sendut Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Sains Malaysia |
content_source |
USM Institutional Repository |
url_provider |
http://eprints.usm.my/ |
language |
English |
topic |
TH1-9745 Building construction |
spellingShingle |
TH1-9745 Building construction Venkateswaran, Chandrasekaran Balaji Murugasan, Rajiah Time Delay and Cost Overrun of Road over Bridge (ROB) Construction Projects in India |
description |
This paper aims at studying the factors that contribute to time delay and cost overrun
of Road over Bridge (ROB) projects in India. Data for the research study were collected from
62 respondents, including owners, contractors, and consultants of ROB projects. The literature
survey and the questionnaire survey helped in identifying 29 factors. The topmost factors were
ranked based on the frequency of occurrences. The correlation among owners, contractors,
and consultants on ranking of factors was derived by Spearman rank correlation. Factor
analysis was used to classify the factors into groups and identify the key groups responsible for
time delay and cost overrun of projects. This study will help all stakeholders of ROB projects in
India to understand the factors and thereby reduce time delay and cost overrun as well as
expedite their completion. |
format |
Article |
author |
Venkateswaran, Chandrasekaran Balaji Murugasan, Rajiah |
author_facet |
Venkateswaran, Chandrasekaran Balaji Murugasan, Rajiah |
author_sort |
Venkateswaran, Chandrasekaran Balaji |
title |
Time Delay and Cost Overrun of Road over Bridge (ROB)
Construction Projects in India |
title_short |
Time Delay and Cost Overrun of Road over Bridge (ROB)
Construction Projects in India |
title_full |
Time Delay and Cost Overrun of Road over Bridge (ROB)
Construction Projects in India |
title_fullStr |
Time Delay and Cost Overrun of Road over Bridge (ROB)
Construction Projects in India |
title_full_unstemmed |
Time Delay and Cost Overrun of Road over Bridge (ROB)
Construction Projects in India |
title_sort |
time delay and cost overrun of road over bridge (rob)
construction projects in india |
publisher |
Penerbit Universiti Sains Malaysia |
publishDate |
2017 |
url |
http://eprints.usm.my/41426/1/jcdc2017.22.s1.5.pdf http://eprints.usm.my/41426/ http://web.usm.my/jcdc/vol22_s1_2017/jcdc2017.22.s1.5.pdf |
_version_ |
1643710218738073600 |