Blue Bay Garments Manufacturing (BBGM) currently offers round necked and collared shirts for men, ladies and kids. Based on the study of BBGM's operations from January to August of 1996, it was determined that the company experienced 33.15% in delivery delays which resulted to P 164,603 in over...

Full description

Saved in:
Bibliographic Details
Main Authors: Baluyut, Mark Kristian, Pinto, Andy
Format: text
Language:English
Published: Animo Repository 1997
Subjects:
Online Access:https://animorepository.dlsu.edu.ph/etd_bachelors/4725
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: De La Salle University
Language: English
id oai:animorepository.dlsu.edu.ph:etd_bachelors-5230
record_format eprints
spelling oai:animorepository.dlsu.edu.ph:etd_bachelors-52302021-02-16T08:38:10Z A system study on the production department of Blue Bay Garments Manufacturing Baluyut, Mark Kristian Pinto, Andy Blue Bay Garments Manufacturing (BBGM) currently offers round necked and collared shirts for men, ladies and kids. Based on the study of BBGM's operations from January to August of 1996, it was determined that the company experienced 33.15% in delivery delays which resulted to P 164,603 in overtime and penalty costs. After an analysis of the possible causes and subcauses that contribute to the delivery delay, it was narrowed down to two controllable causes: BBGM can not meet the monthly job order requirements and the unsystematic acceptance procedure due to the inaccurate due date determination. To solve these causes, the proponents of this study recommend that BBGM increase its production capacity to meet the monthly requirements and develop an acceptance procedure that will accurately determine the due dates of the job orders. A second shift in the production section is proposed to meet the monthly shirt requirements and the pants subcontracting offer. The implementation of the proposal would eliminate the overtime and penalty costs. An additional profit would also be realized from the additional production capacity. BBGM would be able to satisfy the demand and capitalize on the pants opportunity. The Net Present Value of the proposal is P 375,035.92 1997-01-01T08:00:00Z text https://animorepository.dlsu.edu.ph/etd_bachelors/4725 Bachelor's Theses English Animo Repository Clothing trade--Production control Failure analysis (Engineering) Industrial Engineering
institution De La Salle University
building De La Salle University Library
continent Asia
country Philippines
Philippines
content_provider De La Salle University Library
collection DLSU Institutional Repository
language English
topic Clothing trade--Production control
Failure analysis (Engineering)
Industrial Engineering
spellingShingle Clothing trade--Production control
Failure analysis (Engineering)
Industrial Engineering
Baluyut, Mark Kristian
Pinto, Andy
A system study on the production department of Blue Bay Garments Manufacturing
description Blue Bay Garments Manufacturing (BBGM) currently offers round necked and collared shirts for men, ladies and kids. Based on the study of BBGM's operations from January to August of 1996, it was determined that the company experienced 33.15% in delivery delays which resulted to P 164,603 in overtime and penalty costs. After an analysis of the possible causes and subcauses that contribute to the delivery delay, it was narrowed down to two controllable causes: BBGM can not meet the monthly job order requirements and the unsystematic acceptance procedure due to the inaccurate due date determination. To solve these causes, the proponents of this study recommend that BBGM increase its production capacity to meet the monthly requirements and develop an acceptance procedure that will accurately determine the due dates of the job orders. A second shift in the production section is proposed to meet the monthly shirt requirements and the pants subcontracting offer. The implementation of the proposal would eliminate the overtime and penalty costs. An additional profit would also be realized from the additional production capacity. BBGM would be able to satisfy the demand and capitalize on the pants opportunity. The Net Present Value of the proposal is P 375,035.92
format text
author Baluyut, Mark Kristian
Pinto, Andy
author_facet Baluyut, Mark Kristian
Pinto, Andy
author_sort Baluyut, Mark Kristian
title A system study on the production department of Blue Bay Garments Manufacturing
title_short A system study on the production department of Blue Bay Garments Manufacturing
title_full A system study on the production department of Blue Bay Garments Manufacturing
title_fullStr A system study on the production department of Blue Bay Garments Manufacturing
title_full_unstemmed A system study on the production department of Blue Bay Garments Manufacturing
title_sort system study on the production department of blue bay garments manufacturing
publisher Animo Repository
publishDate 1997
url https://animorepository.dlsu.edu.ph/etd_bachelors/4725
_version_ 1772834574597881856