Design & build a protection relay test set

In electrical installations on the main switchboards, protection relays like Overcurrent Relays, Earth Fault Relays, etc. are installed after a Circuit Breaker (CB), designed to trip the respective CB when a fault is detected to protect the end-user / equipment. Shutdown maintenances are carried...

Full description

Saved in:
Bibliographic Details
Main Author: Ong, Vivian Yu Qi
Other Authors: Ling Keck Voon
Format: Final Year Project
Language:English
Published: Nanyang Technological University 2023
Subjects:
Online Access:https://hdl.handle.net/10356/172690
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Nanyang Technological University
Language: English
id sg-ntu-dr.10356-172690
record_format dspace
spelling sg-ntu-dr.10356-1726902023-12-22T15:43:22Z Design & build a protection relay test set Ong, Vivian Yu Qi Ling Keck Voon School of Electrical and Electronic Engineering EKVLING@ntu.edu.sg Engineering::Electrical and electronic engineering::Electric power Engineering::Electrical and electronic engineering::Electric apparatus and materials In electrical installations on the main switchboards, protection relays like Overcurrent Relays, Earth Fault Relays, etc. are installed after a Circuit Breaker (CB), designed to trip the respective CB when a fault is detected to protect the end-user / equipment. Shutdown maintenances are carried out periodically on most electrical installation to test the functionality of components within the electrical installations. As part of the shutdown maintenance work, Secondary Injection (SI) tests are carried out on the protection relays to ensure that the relays are still functioning. Protection relays to be tested can be as much as a hundred relays, all to be tested within a tight time frame. Protection relays found/tested faulty will be highlighted and seek approval from client for immediate replacement. Getting the approval from client will often take time, hence time taken to finish testing all relays is essential. This is to ensure that faulty relays can be replaced within scheduled shutdown timings to avoid delays in restoration of power supply to the estate. The test set that are usually used for the protection relay testing is costly and bulky as it can also carry out other different tests such as Primary Injection test, SI testing of three phase relays which are used in the higher voltage installation. Weighing at more than 20 kilograms (kg), a lot of time and effort is spent moving the bulky and heavy test set around. Regardless of the estate intake capacity, most of them will have a Low Tension (LT) switchboard, up to 400 Volts(V) three-phase line to line, before distribution of power to consumers. Hence, it is very common and mostly only single-phase protection relays to be tested. The other various tests that the bulky test set offers are not required. Hence, the aim of this project is to build a smaller and cheaper SI test set. Bachelor of Engineering (Electrical and Electronic Engineering) 2023-12-18T06:08:53Z 2023-12-18T06:08:53Z 2023 Final Year Project (FYP) Ong, V. Y. Q. (2023). Design & build a protection relay test set. Final Year Project (FYP), Nanyang Technological University, Singapore. https://hdl.handle.net/10356/172690 https://hdl.handle.net/10356/172690 en P1003-221 application/pdf Nanyang Technological University
institution Nanyang Technological University
building NTU Library
continent Asia
country Singapore
Singapore
content_provider NTU Library
collection DR-NTU
language English
topic Engineering::Electrical and electronic engineering::Electric power
Engineering::Electrical and electronic engineering::Electric apparatus and materials
spellingShingle Engineering::Electrical and electronic engineering::Electric power
Engineering::Electrical and electronic engineering::Electric apparatus and materials
Ong, Vivian Yu Qi
Design & build a protection relay test set
description In electrical installations on the main switchboards, protection relays like Overcurrent Relays, Earth Fault Relays, etc. are installed after a Circuit Breaker (CB), designed to trip the respective CB when a fault is detected to protect the end-user / equipment. Shutdown maintenances are carried out periodically on most electrical installation to test the functionality of components within the electrical installations. As part of the shutdown maintenance work, Secondary Injection (SI) tests are carried out on the protection relays to ensure that the relays are still functioning. Protection relays to be tested can be as much as a hundred relays, all to be tested within a tight time frame. Protection relays found/tested faulty will be highlighted and seek approval from client for immediate replacement. Getting the approval from client will often take time, hence time taken to finish testing all relays is essential. This is to ensure that faulty relays can be replaced within scheduled shutdown timings to avoid delays in restoration of power supply to the estate. The test set that are usually used for the protection relay testing is costly and bulky as it can also carry out other different tests such as Primary Injection test, SI testing of three phase relays which are used in the higher voltage installation. Weighing at more than 20 kilograms (kg), a lot of time and effort is spent moving the bulky and heavy test set around. Regardless of the estate intake capacity, most of them will have a Low Tension (LT) switchboard, up to 400 Volts(V) three-phase line to line, before distribution of power to consumers. Hence, it is very common and mostly only single-phase protection relays to be tested. The other various tests that the bulky test set offers are not required. Hence, the aim of this project is to build a smaller and cheaper SI test set.
author2 Ling Keck Voon
author_facet Ling Keck Voon
Ong, Vivian Yu Qi
format Final Year Project
author Ong, Vivian Yu Qi
author_sort Ong, Vivian Yu Qi
title Design & build a protection relay test set
title_short Design & build a protection relay test set
title_full Design & build a protection relay test set
title_fullStr Design & build a protection relay test set
title_full_unstemmed Design & build a protection relay test set
title_sort design & build a protection relay test set
publisher Nanyang Technological University
publishDate 2023
url https://hdl.handle.net/10356/172690
_version_ 1787136723255296000