Formulation of standard test procedure for HALON 1301 total flooding system discharge test
Test procedures for the full scale discharge test of HALON 1301 total flooding system were formulated. The procedures were designed to test the total performance of the 'system', which comprises detection and activation; alarms and displays; protective interlocks; and of course the ability...
Saved in:
Main Author: | |
---|---|
Other Authors: | |
Format: | Research Report |
Published: |
2008
|
Subjects: | |
Online Access: | http://hdl.handle.net/10356/6818 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Nanyang Technological University |
id |
sg-ntu-dr.10356-6818 |
---|---|
record_format |
dspace |
spelling |
sg-ntu-dr.10356-68182023-03-04T18:08:07Z Formulation of standard test procedure for HALON 1301 total flooding system discharge test Wong, Kin Man. School of Mechanical and Production Engineering DRNTU::Engineering::Chemical engineering::Chemical processes Test procedures for the full scale discharge test of HALON 1301 total flooding system were formulated. The procedures were designed to test the total performance of the 'system', which comprises detection and activation; alarms and displays; protective interlocks; and of course the ability of the total flooding system in achieving the key design parameters. ARP-M-20-85 2008-09-17T14:35:11Z 2008-09-17T14:35:11Z 1989 1989 Research Report http://hdl.handle.net/10356/6818 Nanyang Technological University application/pdf |
institution |
Nanyang Technological University |
building |
NTU Library |
continent |
Asia |
country |
Singapore Singapore |
content_provider |
NTU Library |
collection |
DR-NTU |
topic |
DRNTU::Engineering::Chemical engineering::Chemical processes |
spellingShingle |
DRNTU::Engineering::Chemical engineering::Chemical processes Wong, Kin Man. Formulation of standard test procedure for HALON 1301 total flooding system discharge test |
description |
Test procedures for the full scale discharge test of HALON 1301 total flooding system were formulated. The procedures were designed to test the total performance of the 'system', which comprises detection and activation; alarms and displays; protective interlocks; and of course the ability of the total flooding system in achieving the key design parameters. |
author2 |
School of Mechanical and Production Engineering |
author_facet |
School of Mechanical and Production Engineering Wong, Kin Man. |
format |
Research Report |
author |
Wong, Kin Man. |
author_sort |
Wong, Kin Man. |
title |
Formulation of standard test procedure for HALON 1301 total flooding system discharge test |
title_short |
Formulation of standard test procedure for HALON 1301 total flooding system discharge test |
title_full |
Formulation of standard test procedure for HALON 1301 total flooding system discharge test |
title_fullStr |
Formulation of standard test procedure for HALON 1301 total flooding system discharge test |
title_full_unstemmed |
Formulation of standard test procedure for HALON 1301 total flooding system discharge test |
title_sort |
formulation of standard test procedure for halon 1301 total flooding system discharge test |
publishDate |
2008 |
url |
http://hdl.handle.net/10356/6818 |
_version_ |
1759856021412511744 |