New Concepts for Activity Float in Resource-constrained Project Management
The concepts of float and critical path are central to analyzing activity networks in project management. In resource-constrained projects, schedule multiplicity makes it difficult to calculate float and identify critical activities accurately. In this work, new concepts of float and critical activi...
Saved in:
Main Authors: | LIM, Andrew, MA, Hong, RODRIGUES, Brian, TAN, Sun Teck, XIAO, Fei |
---|---|
Format: | text |
Language: | English |
Published: |
Institutional Knowledge at Singapore Management University
2011
|
Subjects: | |
Online Access: | https://ink.library.smu.edu.sg/lkcsb_research/3032 https://doi.org/10.1016/j.cor.2010.10.004 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Singapore Management University |
Language: | English |
Similar Items
-
New concepts for activity float in resource-constrained project management
by: Lim, A., et al.
Published: (2013) -
New Meta-heuristics for the Resource-constrained Project Scheduling Problem
by: LIM, Andrew, et al.
Published: (2013) -
A Hybrid Framework for Over-Constrained Generalized Resource-Constrained Project Scheduling Problems
by: LIM, Andrew, et al.
Published: (2010) -
Over-Constrained Resource-Constrained Scheduling Problems with Prioritized Activities
by: LIM, Andrew, et al.
Published: (2002) -
A Fast Bandwidth Minimization Algorithm
by: LIM, Andrew, et al.
Published: (2007)