Robust execution strategies for project scheduling with unreliable resources and stochastic durations
The resource-constrained project scheduling problem with minimum and maximum time lags (RCPSP/max) is a general model for resource scheduling in many real-world problems (such as manufacturing and construction engineering). We consider RCPSP/max problems where the durations of activities are stochas...