Simulation Study of the Secondary Arc Extinction due to Single Line to Ground Fault on the Thailand 500 kV Line from Mae Moh to Tha Ta Ko
Successful operation of a power system depends largely on the ability to provide reliable and uninterrupted service to the loads. Single phase switching has become an increasingly more viable approach to the operation of EHV systems in recent years. Indeed, single phase reclosing, if successful, rep...
Saved in:
Main Authors: | K. Ngamsanroaj, S. Premrudeepreechacharn, S. Chimklai |
---|---|
Format: | Conference Proceeding |
Published: |
2018
|
Subjects: | |
Online Access: | https://www.scopus.com/inward/record.uri?partnerID=HzOxMe3b&scp=68949208568&origin=inward http://cmuir.cmu.ac.th/jspui/handle/6653943832/60317 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Chiang Mai University |
Similar Items
-
Investigation of single phase reclosing using arc model on the 500 kV transmission line from Mae Moh to Tha Ta Ko
by: K. Ngamsanroaj, et al.
Published: (2018) -
Investigation of single phase reclosing using arc model on the 500 kV transmission line from Mae Moh to Tha Ta Ko
by: K. Ngamsanroaj, et al.
Published: (2018) -
An analysis of single pole reclosing on 500 kV line in Thailand
by: Ngamsanroaj K., et al.
Published: (2014) -
An analysis of single pole reclosing on 500 kV line in Thailand
by: K. Ngamsanroaj, et al.
Published: (2018) -
Evaluation of switching overvoltage in 500 kV transmission line interconnection Nam Theun 2 power plant to Roi Et 2 substation
by: T. Keokhoungning, et al.
Published: (2018)