การวิเคราะห์พฤติกรรมของอุโมงค์ในหินที่ก่อสร้างด้วยเครื่องเจาะอุโมงค์โดยวิธีดิสครีตเอลิเมนต์
The objective of this thesis is to simulate a tunnel model constructed with a tunnel boring machine during construction and to analyze the behavior of the rock mass around the tunnel and the structure of the tunnel. From the project to increase the amount of water in the Mae Kuang Udom Thara res...
Saved in:
Main Author: | |
---|---|
Other Authors: | |
Format: | Theses and Dissertations |
Language: | other |
Published: |
เชียงใหม่ : บัณฑิตวิทยาลัย มหาวิทยาลัยเชียงใหม่
2020
|
Online Access: | http://cmuir.cmu.ac.th/jspui/handle/6653943832/69655 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Chiang Mai University |
Language: | other |
Summary: | The objective of this thesis is to simulate a tunnel model constructed with a tunnel boring
machine during construction and to analyze the behavior of the rock mass around the tunnel and the
structure of the tunnel. From the project to increase the amount of water in the Mae Kuang Udom
Thara reservoir in the Contract 1, Mae Taeng - Mae Ngad water tunnel by the Royal Irrigation
Department Chiang Mai Province from the geological survey data at the entrance-exit number 2, all
behavior was analyzed by the discrete element method using a three-dimensional model. With a
focus on the study of rock mass behavior movement of tunnel structures, stress and strain behavior
around the tunnel in the case that water has not sent into the tunnel yet. To be used as a guideline to
control the behavior of rock movement around the tunnel, especially in the crown and side walls of
the tunnel and the impact on the concrete components from the movement of the surrounding rock
mass
From the study of tunnel construction by tunnel boring machine, the construction can be
classified into 4 steps which are 1) pre-construction step 2) Drilling process 3) Installation steps for
precast concrete tunnel segments and step 4) to increase the stability of the rock mass around the
tunnel by consolidation grouting. Therefore, the study begins with the process of installing the
precast concrete segment as the field data with the motion measurements is done in the said
construction process. In order to use it to create three-dimensional models using 3DEC in other
construction steps, using data from the field. Resulting in a three-dimensional model that can be
modified when needed for further use.
From the processing of the tunnel construction model using tunnel boring machine.
Has no vertical displacement at the tunnel ceiling position. Because the rock mass is in equilibrium
stage in nature. Stress is distributed at the intersection rock joints and increases with depth. And has
no strain occurs at this stage. In the process of excavation a tunnel. The displacement at ceiling is
about 5.67 millimeters. The behavior is characterized by the movement of the down direction along
the joint and the intersection of the rock mass. And there is a deflection on the ground of the tunnel
And the behavior of major principal stress is concentrated on the walls of the tunnels that are dug
and spread along the joints of the rock mass And there is a lot of strain on the ceiling of the tunnel.
In the process of installing precast concrete components The highest movement is found at the
ceiling and raised up at the bottom of the tunnel. The displacement is continue go further from the
excavation step, And the displacement of ceiling is about 6.19 mm and the behavior of the major
principal stress at the wall of the tunnel has slightly decreased. And strain on the tunnel ceiling
slightly decreased after the installation of precast concrete components. In the process of
improvement the stability of the tunnel, The direction of movement remains the same but there is
only a small movement. The movement at the ceiling is approximately 6.21 mm. Stress - Strain does
not change, because the rock mass has moves until it reaches the equilibrium point. |
---|