THE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT)

PT Z did the expansion at Crusher Plant with 49.7 million dollar US Cost. The Expansion was aimed to anticipate the incremental production increase at Grasberg Open Pit Mine in 2008, 2013 and 2014 due to high cut-off grades and also from U/G mine that increase its production to be 80 thousand tons p...

Full description

Saved in:
Bibliographic Details
Main Author: ULYA HIDAYAT (NIM: 29107144), AKHMAD
Format: Theses
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/11772
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:11772
spelling id-itb.:117722017-09-27T15:30:45ZTHE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT) ULYA HIDAYAT (NIM: 29107144), AKHMAD Indonesia Theses INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/11772 PT Z did the expansion at Crusher Plant with 49.7 million dollar US Cost. The Expansion was aimed to anticipate the incremental production increase at Grasberg Open Pit Mine in 2008, 2013 and 2014 due to high cut-off grades and also from U/G mine that increase its production to be 80 thousand tons per day. This project was aimed to anticipate the decrease in production due to hard rock types as well.<p>The role of project management performing to manage limited resources effectively and efficiently to achieve the established target is the key of the successful implementation of those projects. PT Z, established in 1972, still meets the problems in managing its projects. It results in delay of project completion.<p>This Final Project is trying to analyze the project completion delay along with the recommendation of system and procedure to handle it. The research methodology applied is the Five-Stage Problem Solving Process (PSP). PSP is the structurally approach which is describe the problem from the beginning until the implementation of recommendation. The study of this problem include the identification, analysis and the problem solving of the project controlling system and procedure aspect.<p>The things that makes the project completion delay are The limitation and qualification of personil involved; Unclear project priority, organization, system and the procedure of the poject controlling; the limitation of the equipment; material lost and the steel fabrication arrive is not match with Construction sequence.<p>The suggested solutions will include project organization, project priority, project staffing and system & procedure of project planning and controlling. The suggested solutions supported by implementation plan, monitoring plan and management commitment are expected to overcome those problems with the result that project's and company's objective will be accomplished. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description PT Z did the expansion at Crusher Plant with 49.7 million dollar US Cost. The Expansion was aimed to anticipate the incremental production increase at Grasberg Open Pit Mine in 2008, 2013 and 2014 due to high cut-off grades and also from U/G mine that increase its production to be 80 thousand tons per day. This project was aimed to anticipate the decrease in production due to hard rock types as well.<p>The role of project management performing to manage limited resources effectively and efficiently to achieve the established target is the key of the successful implementation of those projects. PT Z, established in 1972, still meets the problems in managing its projects. It results in delay of project completion.<p>This Final Project is trying to analyze the project completion delay along with the recommendation of system and procedure to handle it. The research methodology applied is the Five-Stage Problem Solving Process (PSP). PSP is the structurally approach which is describe the problem from the beginning until the implementation of recommendation. The study of this problem include the identification, analysis and the problem solving of the project controlling system and procedure aspect.<p>The things that makes the project completion delay are The limitation and qualification of personil involved; Unclear project priority, organization, system and the procedure of the poject controlling; the limitation of the equipment; material lost and the steel fabrication arrive is not match with Construction sequence.<p>The suggested solutions will include project organization, project priority, project staffing and system & procedure of project planning and controlling. The suggested solutions supported by implementation plan, monitoring plan and management commitment are expected to overcome those problems with the result that project's and company's objective will be accomplished.
format Theses
author ULYA HIDAYAT (NIM: 29107144), AKHMAD
spellingShingle ULYA HIDAYAT (NIM: 29107144), AKHMAD
THE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT)
author_facet ULYA HIDAYAT (NIM: 29107144), AKHMAD
author_sort ULYA HIDAYAT (NIM: 29107144), AKHMAD
title THE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT)
title_short THE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT)
title_full THE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT)
title_fullStr THE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT)
title_full_unstemmed THE ANALYSIS OF PROJECT COMPLETION DELAY ALONG WITH THE RECOMMENDATION OF THE SYSTEM AND PROCEDURE TO HANDLE IT AT PT. Z (CASE STUDY: CRUSHER MASTER PLAN PROJECT)
title_sort analysis of project completion delay along with the recommendation of the system and procedure to handle it at pt. z (case study: crusher master plan project)
url https://digilib.itb.ac.id/gdl/view/11772
_version_ 1820728308751400960