VOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A
Currently, oil still plays an important role as a source of world energy. Therefore we need a technology that can increase the oil production rate while the demand rate is also increasing. One of the solution is the development of <br /> <br /> <br /> artificial lift. Two kinds o...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/15699 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:15699 |
---|---|
spelling |
id-itb.:156992017-09-27T10:40:53ZVOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A SUSTANTO (NIM : 13106099); Pembimbing : Dr. Ir. Nathanael P.Tandian, FIRDAUS Indonesia Final Project INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/15699 Currently, oil still plays an important role as a source of world energy. Therefore we need a technology that can increase the oil production rate while the demand rate is also increasing. One of the solution is the development of <br /> <br /> <br /> artificial lift. Two kinds of artificial lift methods are progressing cavity pumping (PCP) and electric submersible pumping (ESP). The objectives of this final project are to <br /> <br /> <br /> compare these 2 artificial lifts, to analysis pump volumetric efficiency at involved wells, and to find the best optimization that can be applied to involved wells. The involved wells are AX-100 well and AX-29 well at Melibur Field, Riau and belong to Kondur Petroleum S.A. <br /> <br /> <br /> The average volumetric efficiencies of progressing cavity pump Moyno 20- H-200 which is being operated at AX-100 well are 42% and 80%. At AX-29 well, there is electric submersible pump Centrilift P-22-400 whose average volumetric efficiency is 57%. The optimization for AX-100 well is change pump rotation from 108 RPM into 210 RPM and the production target is 407 BFPD. For AX-29, the <br /> <br /> <br /> optimization is change the pump installation with new progressing cavity pump, Moyno 15-H-950 at 800 feet as a pump setting depth .The production target of this well is 1.880 BFPD. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
Currently, oil still plays an important role as a source of world energy. Therefore we need a technology that can increase the oil production rate while the demand rate is also increasing. One of the solution is the development of <br />
<br />
<br />
artificial lift. Two kinds of artificial lift methods are progressing cavity pumping (PCP) and electric submersible pumping (ESP). The objectives of this final project are to <br />
<br />
<br />
compare these 2 artificial lifts, to analysis pump volumetric efficiency at involved wells, and to find the best optimization that can be applied to involved wells. The involved wells are AX-100 well and AX-29 well at Melibur Field, Riau and belong to Kondur Petroleum S.A. <br />
<br />
<br />
The average volumetric efficiencies of progressing cavity pump Moyno 20- H-200 which is being operated at AX-100 well are 42% and 80%. At AX-29 well, there is electric submersible pump Centrilift P-22-400 whose average volumetric efficiency is 57%. The optimization for AX-100 well is change pump rotation from 108 RPM into 210 RPM and the production target is 407 BFPD. For AX-29, the <br />
<br />
<br />
optimization is change the pump installation with new progressing cavity pump, Moyno 15-H-950 at 800 feet as a pump setting depth .The production target of this well is 1.880 BFPD. |
format |
Final Project |
author |
SUSTANTO (NIM : 13106099); Pembimbing : Dr. Ir. Nathanael P.Tandian, FIRDAUS |
spellingShingle |
SUSTANTO (NIM : 13106099); Pembimbing : Dr. Ir. Nathanael P.Tandian, FIRDAUS VOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A |
author_facet |
SUSTANTO (NIM : 13106099); Pembimbing : Dr. Ir. Nathanael P.Tandian, FIRDAUS |
author_sort |
SUSTANTO (NIM : 13106099); Pembimbing : Dr. Ir. Nathanael P.Tandian, FIRDAUS |
title |
VOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A |
title_short |
VOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A |
title_full |
VOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A |
title_fullStr |
VOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A |
title_full_unstemmed |
VOLUMETRIC EFFICIENCY ANALYSIS AND OPTIMIZATION OF PROGRESSING CAVITY PUMP AND ELECTRIC SUBMERSIBLE PUMP AT MELIBUR FIELD, KONDUR PETROLEUM S.A |
title_sort |
volumetric efficiency analysis and optimization of progressing cavity pump and electric submersible pump at melibur field, kondur petroleum s.a |
url |
https://digilib.itb.ac.id/gdl/view/15699 |
_version_ |
1820737526540795904 |