RISK ANALYSIS OF LIGHT RAIL TRANSIT TRACKWORK (A CASE STUDY OF PT. WIJAYA KARYA BETON)
PT. Wijaya Karya Beton is an Indonesia-based construction company with precast concrete as the main <br /> <br /> product. In recent years, PT. WIKA Beton have been producing other construction products such as PC <br /> <br /> Poles, PC Piles, Railway Sleepers, Bridge Concre...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/28060 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | PT. Wijaya Karya Beton is an Indonesia-based construction company with precast concrete as the main <br />
<br />
product. In recent years, PT. WIKA Beton have been producing other construction products such as PC <br />
<br />
Poles, PC Piles, Railway Sleepers, Bridge Concrete, Retaining Wall, Hydro Structure, Buildings and <br />
<br />
Houses, Marine Structure, and PC Cylinder piles. As one of the contractor for the project of Light Rail <br />
<br />
Transit (LRT) track work construction in DKI Jakarta, PT. WIKA Beton have the obligation to ensure <br />
<br />
failure or defect in the process will not take place. <br />
<br />
This study aims to identify and detect the potential failure or defect in the process of Light Rail Transit <br />
<br />
track work and give the most appropriate solution in ensuring the project is running smoothly by <br />
<br />
analyzing using the Failure Modes and Effect Analysis (FMEA). The method is leading the <br />
<br />
organization to anticipate the failure or defect by ranking the potential failure or defect in order to <br />
<br />
make the best decision. <br />
<br />
Quantitative and qualitative data from PT. WIKA Beton are showing the possibility of failure in the <br />
<br />
track work. From the analysis of the data it yields that several main causes contributes to failures, in <br />
<br />
which the several causes can be categorized as high risk, medium risk, and low risk. This study focuses <br />
<br />
on possible high-risk causes such as scheduled delay, tax payment differences, possible burning in the <br />
<br />
process, and fluctuation of material prices. Relevant with the issues, a solution is using proposed using <br />
<br />
project management method by using AON model to provide appropriate recommendation overcoming <br />
<br />
the issues. This study is conducted with the expectation that the result can be considerations for PT. <br />
<br />
WIKA Beton in making the right decisions for the track work project. |
---|