COMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN
In a construction site, there are often found soil condition that are not in accordance with the existing design criteria, so it need some improvement for get a better soil condition. On the land preparation at coal terminal project of the ports on the Lubuk Tutung area, East Kalimantan, there are f...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/35356 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:35356 |
---|---|
spelling |
id-itb.:353562019-02-25T12:19:11ZCOMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN Nosa A, Anggoro Teknik (Rekayasa, enjinering dan kegiatan berkaitan) Indonesia Final Project Soil improvement method, Prefabricated vertical drain, Sand compaction pile. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/35356 In a construction site, there are often found soil condition that are not in accordance with the existing design criteria, so it need some improvement for get a better soil condition. On the land preparation at coal terminal project of the ports on the Lubuk Tutung area, East Kalimantan, there are founded that the bearing capacity of the soil is 44 kN/m2 and settlement of soil is 0.84 m by the time it takes as many as 322 Years, and it is not suitable according to design criteria. By it condition, the soil was proposed to get two soil improvement method, which is prefabricated vertical drains and sand compaction pile, where both methods will be compared in this research. The first soil improvement method, prefabricated vertical drains method, is accelerated the time to reach the final stage of settlement with the gradual accumulation with the time it takes for 10 months, but this method cannot reduce the size of the soil settlement. The second method, the sand compaction pile method, can reduce the size of the settlement that occurred at 0.41 m in 13 months, so the use of the sand compaction pile method is more effective than the use of prefabricated vertical drain soil improvement method for improving the soil condition. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Teknik (Rekayasa, enjinering dan kegiatan berkaitan) |
spellingShingle |
Teknik (Rekayasa, enjinering dan kegiatan berkaitan) Nosa A, Anggoro COMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN |
description |
In a construction site, there are often found soil condition that are not in accordance with the existing design criteria, so it need some improvement for get a better soil condition. On the land preparation at coal terminal project of the ports on the Lubuk Tutung area, East Kalimantan, there are founded that the bearing capacity of the soil is 44 kN/m2 and settlement of soil is 0.84 m by the time it takes as many as 322 Years, and it is not suitable according to design criteria. By it condition, the soil was proposed to get two soil improvement method, which is prefabricated vertical drains and sand compaction pile, where both methods will be compared in this research.
The first soil improvement method, prefabricated vertical drains method, is accelerated the time to reach the final stage of settlement with the gradual accumulation with the time it takes for 10 months, but this method cannot reduce the size of the soil settlement. The second method, the sand compaction pile method, can reduce the size of the settlement that occurred at 0.41 m in 13 months, so the use of the sand compaction pile method is more effective than the use of prefabricated vertical drain soil improvement method for improving the soil condition. |
format |
Final Project |
author |
Nosa A, Anggoro |
author_facet |
Nosa A, Anggoro |
author_sort |
Nosa A, Anggoro |
title |
COMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN |
title_short |
COMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN |
title_full |
COMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN |
title_fullStr |
COMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN |
title_full_unstemmed |
COMPARATIVE ANALYSIS METHOD OF SOFT SOIL IMPROVEMENT PREFABRICATED VERTICAL DRAIN WITH SAND COMPACTION PILE, CASE STUDY OF LAND PREPARATION COAL TERMINAL PORT SITE, LUBUK TUTUNG KALIMANTAN |
title_sort |
comparative analysis method of soft soil improvement prefabricated vertical drain with sand compaction pile, case study of land preparation coal terminal port site, lubuk tutung kalimantan |
url |
https://digilib.itb.ac.id/gdl/view/35356 |
_version_ |
1821996911741108224 |