"DESIGN OF BORED PILE FOUNDATION AND BASEMENT RETAINING WALLS IN INDONESIAN TRADITIONAL GAME MUSEUM IN JAKARTA PUSAT"; and " DRAINAGE SYSTEM DESIGN OF INDONESIAN MUSEUM OF PERMAINAN TRADISIONAL"
ABSTRACT 1: "Based on architectural drawings, the geotechnical aspect planning requirements were formulated on the Indonesian Traditional Games Museum Project namely foundation and retaining wall. The foundation serves to hold and channel the load given the upper structure to the base soil...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/40376 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | ABSTRACT 1:
"Based on architectural drawings, the geotechnical aspect planning requirements
were formulated on the Indonesian Traditional Games Museum Project namely
foundation and retaining wall. The foundation serves to hold and channel the load
given the upper structure to the base soil, while the retaining wall functions to hold
the soil around the existing basement excavation.
The stages of this final project are divided into two, namely starting from the
planning of the foundation and followed by planning the retaining wall in the
basement. The type of foundation used in this final project is drill pile foundation,
while the type of soil retaining wall chosen is diaphragm wall. The foundation
planning stage starts from the interpretation of land data according to the results
of testing both direct testing and laboratory test results. Furthermore, the
interpretation of the upper structure load will then determine the dimensions and
configuration of the foundation to be used. After that, a large decrease in
foundation and deflection is carried out on the foundation.
The stages of planning the design of the retaining wall begin with the interpretation
of soil data, then determine the depth of penetration of the retaining wall with
manual calculations, then proceed with modeling the retaining wall using the
program. Then check the value of safety factors for sliding, rolling, global stability
and the collapse of excavation of the design used. Planning the design of drill pile foundation and retaining wall in this final project uses several assistance programs such as LPILE, GROUP, CSICol, Plaxis 2D 2017
and AutoCAD 2017. The outputs obtained from the planning of foundation and
retaining walls are dimensions, reinforcement, and images technique."
ABSTRACT 2:
"Drainage design in an area must be based on calculations and analysis in
accordance with applicable standards, so that the design can channel all the runoff
of rainwater that falls in the area. The drainage system planned in this Final Project
Design is surface drainage by using a planned rainfall log-pearson type III
probability method for a 2 year return period. The design is carried out using the
guide book for the Procedure for Arranging the Master Plan for the Urban
Drainage System of the Ministry of Public Works of the Directorate General of
Human Settlements, with the use of 10-year rainfall data sourced from the BMKG
online site. The results of the design dimensions of the drainage channel used are
type I size 0.4 mx 0.4 m, type II size 0.6 mx 0.6 m, and type III size 0.8 mx 0.8 m,
with precast U concrete material -ditch." |
---|