STUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER

This study discusses the determination of measures that can be done to reduce the risk of tsunami disasters faced by the Pelabuhan Ratu steam power plant. This research was carried out by a literature study to ascertain the impact of tsunami and finding the existing tsunami risk reduction measures o...

Full description

Saved in:
Bibliographic Details
Main Author: Rory Abduljabbar, Muhammad
Format: Final Project
Language:Indonesia
Online Access:https://digilib.itb.ac.id/gdl/view/46910
Tags: Add Tag
No Tags, Be the first to tag this record!
Institution: Institut Teknologi Bandung
Language: Indonesia
id id-itb.:46910
spelling id-itb.:469102020-03-13T09:15:24ZSTUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER Rory Abduljabbar, Muhammad Indonesia Final Project Tsunami, Risk Reduction, gap analysis, Pelabuhan Ratu Steam Power plant. INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/46910 This study discusses the determination of measures that can be done to reduce the risk of tsunami disasters faced by the Pelabuhan Ratu steam power plant. This research was carried out by a literature study to ascertain the impact of tsunami and finding the existing tsunami risk reduction measures of the steam power plant through interview, to be analyzed for improvement. This research then collected as much measures as possible to be used to reduce the risk of tsunamis through a literature study, and then these measures were divided into two, namely structural and non-structural. From the literature study, there were seven structural and five non-structural measures, each of the measures is then discussed about the general picture and its application at the steam power plant with the use of gap analysis to see the possibility of implementation or quality improvement. From 7 structural measures, three are not owned, and the remaining four are owned, for the three measures that are not yet owned, it is recommended to be owned, and for four that are already owned, it is recommended to be improved for more impactful results. Of the five non-structural measures, all of them are recommended by the author to be owned by the steam power plant because these measures are easy to do and not too expensive but significantly affecting the tsunami risk reduction in the steam power plant. Improvements also proposed for evacuation plan consist of simplifying scenario, adding new shelter and evacuation route adjustment. The results of this study are expected to help steam power plant to realize that they are facing the risk of the tsunami disaster and can take action with risk reduction measures that have been collected and discussed one by one for the benefit of steam power plant. text
institution Institut Teknologi Bandung
building Institut Teknologi Bandung Library
continent Asia
country Indonesia
Indonesia
content_provider Institut Teknologi Bandung
collection Digital ITB
language Indonesia
description This study discusses the determination of measures that can be done to reduce the risk of tsunami disasters faced by the Pelabuhan Ratu steam power plant. This research was carried out by a literature study to ascertain the impact of tsunami and finding the existing tsunami risk reduction measures of the steam power plant through interview, to be analyzed for improvement. This research then collected as much measures as possible to be used to reduce the risk of tsunamis through a literature study, and then these measures were divided into two, namely structural and non-structural. From the literature study, there were seven structural and five non-structural measures, each of the measures is then discussed about the general picture and its application at the steam power plant with the use of gap analysis to see the possibility of implementation or quality improvement. From 7 structural measures, three are not owned, and the remaining four are owned, for the three measures that are not yet owned, it is recommended to be owned, and for four that are already owned, it is recommended to be improved for more impactful results. Of the five non-structural measures, all of them are recommended by the author to be owned by the steam power plant because these measures are easy to do and not too expensive but significantly affecting the tsunami risk reduction in the steam power plant. Improvements also proposed for evacuation plan consist of simplifying scenario, adding new shelter and evacuation route adjustment. The results of this study are expected to help steam power plant to realize that they are facing the risk of the tsunami disaster and can take action with risk reduction measures that have been collected and discussed one by one for the benefit of steam power plant.
format Final Project
author Rory Abduljabbar, Muhammad
spellingShingle Rory Abduljabbar, Muhammad
STUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER
author_facet Rory Abduljabbar, Muhammad
author_sort Rory Abduljabbar, Muhammad
title STUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER
title_short STUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER
title_full STUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER
title_fullStr STUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER
title_full_unstemmed STUDY OF RISK REDUCTION IN PELABUHAN RATU STEAM POWER PLANT TOWARD TSUNAMI DISASTER
title_sort study of risk reduction in pelabuhan ratu steam power plant toward tsunami disaster
url https://digilib.itb.ac.id/gdl/view/46910
_version_ 1822927514090078208