PRECAST SLAB SYSTEM DESIGN FROM BASEMENT TO PODIUM FLOORS AT THE 2X8 PARK APARTMENT PROJECT OF CIBADAK AREA IN BANDUNG
Bandung, as the capital city of West Java Province in Indonesia, is a city with population density reached up to 2.498 million people and population growth rate 0.29%/year in 2017. One of the locations in the center of Bandung which is a tourist attraction as well as an economic center is Cibadak...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/48468 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | Bandung, as the capital city of West Java Province in Indonesia, is a city with
population density reached up to 2.498 million people and population growth rate
0.29%/year in 2017. One of the locations in the center of Bandung which is a tourist
attraction as well as an economic center is Cibadak which is located in
Karanganyar District. Similar to Bandung, the rate of population growth in that
area also increases every year. This condition leads to the increase of the
residential demand in Cibadak. Thus, vertical residence/ apartment then offered as
the solution since it does not require much space that will be designed in this thesis
as 2x8 Park Apartment Project of Cibadak Area in Bandung. From basement to
podium floors, it is planned to use precast slabs with additional cast in situ slabs in
several locations. The scope of this thesis generally covers: design of precast slabs
which includes dimension, reinforcement, and connection; planning of construction
method of the precast slabs; and do a cost comparison analysis between precast
slabs and if cast in situ slabs are used throughout the floors. The type of precast
slab used is Hollow Core Slab with thickness of 150 mm, 50 mm thick overtopping,
width varies between 1200 mm – 2000 mm, and length varies between 1600 mm –
7625 mm. The reinforcement used in the precast slabs is non-prestressed
reinforcement while the connection uses a wet connection. The construction method
of the precast slabs includes: fabrication, transportation, and installation. The cost
requires for the construction of precast slabs system on Basement 1st floor, Podium 1st floor, and Podium 2nd floor is Rp. 4,608,443,554 or 36.22% smaller compared to
if the entire floor uses cast in situ slabs. |
---|