STUDY OF SOCIAL ECONOMIC OF POST PRODUCTION ARUN LNG REFINERY UTILIZATION AS LNG RECEIVING TERMINAL AND REGASIFICATION UPONLOCAL ECONOMY
The aim of study is the development analysis of post production Arun LNG refinery whose period of operation since 1978 will be the end by 2014, then utilized as LNG receiving terminal and regasification is useful to satisfy gas requirement in Aceh and North Sumatera regions. The Arun refinery may...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/54662 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
Summary: | The aim of study is the development analysis of post production Arun LNG refinery whose
period of operation since 1978 will be the end by 2014, then utilized as LNG receiving
terminal and regasification is useful to satisfy gas requirement in Aceh and North Sumatera
regions. The Arun refinery may be modified into LNG receiving terminal and regasification
tanks to some well, reasonable facilities on available to use. To realize the feasibility of a
project, a study of economy was conducted in 2 years period of improvement, 20 years
operation, and supply of LNG some 150 MMSCFD for first year, 200 MMSCFD second
year, rise to 250 MMSCFD in third year, to 300 MMSCFD fourth year and to 350 MMSCFD
fifth year to twentieth year for maximum capacity of production. The study of the project
feasibility is carried out by way of 3 parameters: NPV, IRR and BCR. As for the result
economic analysis feasible in whith the NPV is US$ 889.774 million, IRR 19%, B/CRatio 4.
PT. Arun was delivering significant contributions of North Aceh economic composing
sectors; it is visible in 1978-2005, as oil and gas rose from IDR 120 billion in 1978 to IDR
7.79 trillion in 2005 with 26% average rate of growth per year. In 1978 regional gross
domestic product rose from IDR 42.78 billion to IDR 2.15 trillion in 2005 with 23% average
rate of growth per year, while in reduction of 2006-2012 North Aceh Regional Gross
Domestic Product on base year of 2000 constant price, a reduction of IDR 7.68 trillion in
2006 to IDR 4.32 trillion in 2012. Average rate of growth minus nine percent (-9%) per year
(with oil and natural gas); while without oil and natural gas, the Regional Goss Domestic
Product of North Aceh in 2006 is IDR 2.46 trillion, it is rising to IDR 3.07 trillion in 2012.
Based on the mean rate of growth (4%) per year, the condition reflects potential decline of
local output and their considerable relevance to decrease in production of PT. Arun.
Based on the study, the Arun LNG Refinery utilization will be delivering contribution of
GRDP based on 2000 constant price some IDR 1.081 trillion in 2015, rise to IDR 2.651
trillion in 2034 and the rate of growth at 16% per year. When the degree of change in GRDP
(?Y) is related to Arun LNG Refinery Utilization, the projection of investment and job
opportunity for formation of GRDP per year will be discovered. In 2016, the PT. Arun may
produce job opportunities (?N) for 84.477 people or 5.280 people per rise of 1.0% GRDP.
Furthermore, in 2034 the job opportunities have reduction to 5.277 people or 330 people per
rise of 1.0% GRDP. By the year of projection, mean value of labor (?L) is IDR 138.49
billion and mean job opportunity (?N) is 18.411 people or 1.153 people per rise of 1.0%
GRDP. The rate of investment in 2016 is IDR 202.60 billion; it is possible will be declining
to IDR 1.10 trillion in 2020. Subsequently, by 2021 the rate will have rise some IDR 1.32
billion to IDR 12.65 billion in 2034. It is, of course, accompanied by change in investment
during period of 2015-2034 at, on average, IDR 46.55 billion per year. Growth rate of labor
productivity decline, this is due to the growth of labor is higher than the growth of capital
and capital productivity would other wise rise. Labor productivity level in capital-labor ratio
in Y/L and Y/K with LNG Refinery utilization larger than Y/L and Y/K without Arun LNG
Refinery utilization.This project have net social gain (NSG) in 2015 IDR 72.12 billion with
net gain coefficient (NGC) some 6.70% had increase in 2034 some IDR 91.44 billion or
NGC some 3.64% with average NGC some 3.77% per annum. |
---|