CONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG
The Kebon Kawung Accessible Hub Development Project is located at the Bandung Railway Station and stretches from the north side of the station (Jalan Kebon Kawung No. 43 Bandung) to the south side of the station (Jalan Timur Station No. 1 Bandung). The land area of this project is 21,500 m2 and t...
Saved in:
Main Author: | |
---|---|
Format: | Final Project |
Language: | Indonesia |
Online Access: | https://digilib.itb.ac.id/gdl/view/67943 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:67943 |
---|---|
spelling |
id-itb.:679432022-08-29T09:50:38ZCONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG Matheus Nasution, Redi Indonesia Final Project Implementation Method, Budget Plan, Scheduling, S-Curve, Kebon Kawung, Accessible Hub INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/67943 The Kebon Kawung Accessible Hub Development Project is located at the Bandung Railway Station and stretches from the north side of the station (Jalan Kebon Kawung No. 43 Bandung) to the south side of the station (Jalan Timur Station No. 1 Bandung). The land area of this project is 21,500 m2 and the building area is 9,500 m2. This project consists of 3 floors and 1 mezzanine. The lower structure uses bored pile foundations and the upper structure uses reinforced concrete. In this final project, 1 type of formwork is used, namely conventional formwork with scaffolding and temporary portal scaffolding for work areas on active railroads. Calculation of time and cost is calculated based on the implementation method in accordance with the theory from various references used. The purpose of the preparation of this final project is to obtain the right construction method and the optimal point of the relationship between project time and cost. For scheduling each work item, it is done using the Ms. Projects. The final results obtained are the implementation method, duration, budget plan and S curve. Based on the analysis, the duration is 364 working days with an implementation cost budget of Rp.70 billion. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
description |
The Kebon Kawung Accessible Hub Development Project is located at the Bandung
Railway Station and stretches from the north side of the station (Jalan Kebon
Kawung No. 43 Bandung) to the south side of the station (Jalan Timur Station No.
1 Bandung). The land area of this project is 21,500 m2 and the building area is 9,500
m2. This project consists of 3 floors and 1 mezzanine. The lower structure uses
bored pile foundations and the upper structure uses reinforced concrete. In this final
project, 1 type of formwork is used, namely conventional formwork with
scaffolding and temporary portal scaffolding for work areas on active railroads.
Calculation of time and cost is calculated based on the implementation method in
accordance with the theory from various references used. The purpose of the
preparation of this final project is to obtain the right construction method and the
optimal point of the relationship between project time and cost. For scheduling each
work item, it is done using the Ms. Projects. The final results obtained are the
implementation method, duration, budget plan and S curve. Based on the analysis,
the duration is 364 working days with an implementation cost budget of Rp.70
billion. |
format |
Final Project |
author |
Matheus Nasution, Redi |
spellingShingle |
Matheus Nasution, Redi CONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG |
author_facet |
Matheus Nasution, Redi |
author_sort |
Matheus Nasution, Redi |
title |
CONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG |
title_short |
CONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG |
title_full |
CONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG |
title_fullStr |
CONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG |
title_full_unstemmed |
CONSTRUCTION MANAGEMENT PLAN OF ACCESSIBLE HUB AT KEBON KAWUNG TRAIN STATION AREA BANDUNG |
title_sort |
construction management plan of accessible hub at kebon kawung train station area bandung |
url |
https://digilib.itb.ac.id/gdl/view/67943 |
_version_ |
1822278070900359168 |