DESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA
Current performance management for project execution in the Company is measured with the strategy and process on how to achieve the target based on technical guidelines. Critical decision-making mostly depends on management’s experiences. The Company’s position as State-Owned Enterprises in Indon...
Saved in:
Main Author: | |
---|---|
Format: | Theses |
Language: | Indonesia |
Subjects: | |
Online Access: | https://digilib.itb.ac.id/gdl/view/71771 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Institution: | Institut Teknologi Bandung |
Language: | Indonesia |
id |
id-itb.:71771 |
---|---|
spelling |
id-itb.:717712023-02-23T09:31:17ZDESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA Bani Perwira, Yosephus Manajemen umum Indonesia Theses Key Performance Indicator, Oil and Gas, Performance Management System, Performance Prism INSTITUT TEKNOLOGI BANDUNG https://digilib.itb.ac.id/gdl/view/71771 Current performance management for project execution in the Company is measured with the strategy and process on how to achieve the target based on technical guidelines. Critical decision-making mostly depends on management’s experiences. The Company’s position as State-Owned Enterprises in Indonesia receives high expectations from stakeholders. The complexity of the business has made the development of the Performance Management System (PMS) for oil and gas project in the Company, is important as basis and guideline to overcome the issues. This final project aims to design an appropriate PMS and identify important Key Performance Indicators (KPI) that can be implemented during the execution of oil and gas project in the Company. The design was developed from specific literature Performance Prism and previous project’s lessons learned, which elaborated the various stakeholders point of views, combined with cascading process in employee levels and presented the linkages using weight ratio. The questionnaire was addressed to various stakeholders who were involved in the project execution. There were 31 respondents who selected 90 KPIs and gave ratings on current performance. The weight ratio of defined criteria, sub-criteria and KPI was calculated using Analytical Hierarchy Process. The scoring system was conducted using the Objective Matrix and Traffic Light System to evaluate the performance. Findings of this final project provide totally 61 KPIs as leading indicators that are useful to design PMS. These KPIs to be implemented from early stage of new project or on-going project in the Company. Further benchmarking to the other sister companies within subsidiary is required to identify the best KPI approach. text |
institution |
Institut Teknologi Bandung |
building |
Institut Teknologi Bandung Library |
continent |
Asia |
country |
Indonesia Indonesia |
content_provider |
Institut Teknologi Bandung |
collection |
Digital ITB |
language |
Indonesia |
topic |
Manajemen umum |
spellingShingle |
Manajemen umum Bani Perwira, Yosephus DESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA |
description |
Current performance management for project execution in the Company is
measured with the strategy and process on how to achieve the target based on
technical guidelines. Critical decision-making mostly depends on management’s
experiences. The Company’s position as State-Owned Enterprises in Indonesia
receives high expectations from stakeholders. The complexity of the business has
made the development of the Performance Management System (PMS) for oil and
gas project in the Company, is important as basis and guideline to overcome the
issues.
This final project aims to design an appropriate PMS and identify important Key
Performance Indicators (KPI) that can be implemented during the execution of oil
and gas project in the Company. The design was developed from specific literature
Performance Prism and previous project’s lessons learned, which elaborated the
various stakeholders point of views, combined with cascading process in employee
levels and presented the linkages using weight ratio.
The questionnaire was addressed to various stakeholders who were involved in the
project execution. There were 31 respondents who selected 90 KPIs and gave
ratings on current performance. The weight ratio of defined criteria, sub-criteria and
KPI was calculated using Analytical Hierarchy Process. The scoring system was
conducted using the Objective Matrix and Traffic Light System to evaluate the
performance.
Findings of this final project provide totally 61 KPIs as leading indicators that are
useful to design PMS. These KPIs to be implemented from early stage of new
project or on-going project in the Company. Further benchmarking to the other
sister companies within subsidiary is required to identify the best KPI approach. |
format |
Theses |
author |
Bani Perwira, Yosephus |
author_facet |
Bani Perwira, Yosephus |
author_sort |
Bani Perwira, Yosephus |
title |
DESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA |
title_short |
DESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA |
title_full |
DESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA |
title_fullStr |
DESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA |
title_full_unstemmed |
DESIGN OF PERFORMANCE MANAGEMENT SYSTEM USING PERFORMANCE PRISM FOR OIL AND GAS PROJECT: CASE STUDY BKP OFFSHORE BROWNFIELD PROJECT IN MAHAKAM DELTA, EAST KALIMANTAN, INDONESIA |
title_sort |
design of performance management system using performance prism for oil and gas project: case study bkp offshore brownfield project in mahakam delta, east kalimantan, indonesia |
url |
https://digilib.itb.ac.id/gdl/view/71771 |
_version_ |
1822992272901275648 |